Center Infrastructure Improvement Project Newsletter

Plan Ahead: Construction & Community Updates

The Metropolitan District Commission's (MDC) contractor will be performing sanitary sewer repairs on Farmington Avenue during the weeks of November 3 and November 10. Work will take place in segments between Dale Street and South Main Street. While this activity may cause minor disruptions, the Town and MDC appreciate your patience as we continue these important improvements.


Additionally, on Wednesday, November 5, Gerber Construction is planning to pave LaSalle Road (weather dependent). Please note:

  • Parking on LaSalle Road may be limited in the afternoon from Arapahoe to Farmington.
  • Traffic disruptions are expected:
  • Morning: parking lane along the west side of LaSalle Road from Farmington Avenue to Arapahoe Road
  • Afternoon: LaSalle Road - Arapahoe Road to Ellsworth Road (full width)
  • Traffic control will maintain alternating one-lane traffic along the entire street during paving.
  • Pavement markings will follow soon after and should be completed within a few hours. During this time, parking will be limited on the west side of LaSalle Road and from Arapahoe Road to Ellsworth Road.



We thank the community for your understanding as we continue the West Hartford Center improvements.

Project Progess

Construction activity continues to make steady progress along LaSalle Road.

  • Tree planting has officially begun, bringing new landscaping to the Center.
  • In Phase 3A, most of the concrete work is expected to be completed this week, weather permitting. The majority of curbing in this area is now in place.
  • Installation of Rectangular Rapid Flashing Beacons (RRFBs) for pedestrian crossings is also underway.

Two-Week Look Ahead

October 28 – November 1

Sitewide

  • Delivery and installation of trees will continue throughout the week.
  • Gerber Construction will continue resetting manholes along LaSalle Road and perform paving as needed.

Phase 3A

  • Sidewalk grading will continue.
  • Crews will begin setting curbs and pouring sidewalks.



November 3 – November 7

Sitewide

  • Tree and shrub planting will continue across the site.

Phase 3A

  • Grading and sidewalk work will continue in this area.

Phase 3B

  • Gerber Construction will install storm drainage at the corner of Ellsworth and LaSalle.


Phase 3A

Phase 3B

Friendly Toast (Between 2A/3A)

William Raveis

Top Level Salon


Lux Bond & Green


Store52


More Italian Pasta Lab


AT&T


Cook Shop Plus


Block Advisors


Harvest Wine Bar & Restaurant


Matthew Phillips Salon


Song Restaurant


Qais Convenience Shop


NY Deli & Grill


Restaurant Bricco


Hard Hats Meet Hashtags

For regular updates and photos from the West Hartford Center Project, follow us on Instagram. Stay informed about ongoing work, progress, and what’s next for the project.

ATTENTION: Local Businesses - Get the Business Toolkit

Signage to Help Keep Your Business and Customers Informed!

In this Toolkit:

  • Business Rack Cards- Tips
  • Business Placards- Click link below to see customized window and/or cash wrap signage for your industry!

If you need additional copies of outreach materials, such as window signs, or have any questions, please feel free to contact us at CenterConstruction@westhartfordct.gov — we’re happy to assist.

As construction progresses, we're working to maximize on-street parking for customers and visitors. To help, we encourage employees to use alternative parking options, including the Town Center Parking Garage, which offers reduced rates for retail and restaurant employees working in the Center.


The Town Center Garage rates are far lower than other options! The rates are $4.50 for up to an 8.5-hour shift and $7 for anything over 8.5 hours.


For more info, contact Kristen Gorski, Economic Development Manager, at kristen.gorski@westhartfordct.gov..

The Retail Validation Program:

A Reduced Rate Employee Parking Option for Your Staff

Stay Informed and Ahead of the Curve

For the latest updates and important information about the project, visit our project webpage. It’s your go-to resource for all the news, timelines, and tools to help your business navigate the construction period smoothly.

Have questions or feedback? We’re here to help—email us at CenterConstruction@westhartfordct.gov