Dear Members,


This is a quick update for Day 5, May 26th, of the Single Family HOA Repaving Project. The contractor is completing the final removal of some of the remaining asphalt on all the streets. Some old stable asphalt may still remain in isolated spots due to the depth of the old roadway base. Our engineering firm assures us that it will not be an issue as the new pavement is installed over it at an average compacted depth of 1.5 inches.


The contractor has completed repairing all the concrete gutters that were indicated for replacement. They are now starting on the installation of the underground conduits to each cul-de-sac, starting on Rolling Oaks.


The schedule for repaving is dependent on the progress of the above work and the weather, but it looks like the new paving installation might start as early as today Friday May 26 or by May 30 with an initial leveling rough course. We’ve instructed the contractor that no major finished paving work is to be done on May 30th due to the presence of the garbage and recycle trucks.


Repaving work would most likely start at the north end of our property and head south. Each roadway should take a day to complete the paving work. During the paving operation, roadway access will be limited to local residents only. Once the paving process starts, a black liquid tack material will be applied on the roadway several hundred feet ahead of the paving machine. Do not drive on the tack material as it will adhere to your tires and it would track into your driveway.  


We will keep you informed of the progress and schedule with an email later this week.


Thank you,


The Strand Single Family HOA Board of Directors