FAQs & Project Related Topics
Completion Outlook
Currently, the construction project is behind schedule by about 8 weeks from the originally projected time of completion. Aside from just pavement and curb being installed, there are other miscellaneous construction activities that need to take place before the roadway can be open to through traffic. As roadway construction continues to progress, the roadway is scheduled to be open to traffic in the next few weeks. Meanwhile, access will be restricted to local residents only.
Water Service Hook Ups
For those residents who are interested in the connection to City Water, please visit the city's website.
Turf Restoration
Turf restoration is scheduled to take place after the roadway is paved and general pavement and concrete repairs are completed. In the meantime, crews will be slowly excavating and removing miscellaneous debris and excess soils from the boulevard area as the road section construction is being completed. Turf seeding will take place this fall, but final turf seeding and touch ups will take place in the Spring of 2024.
Contractors will be responsible for watering lawns for 30 days, at which time residents will be notified that they are to take over maintenance (i.e. watering, mowing).
Tree Planting
Tree planting handouts will be provided in November. Trees will be available for delivery in the Spring of 2024.
Irrigation Repair
Irrigation repair is completed for the year. Any remaining repair items will be adjusted and repaired in the spring.
Topsoil Installation
Not all current boulevard conditions are finalized yet. Boulevard cleanup and imported topsoil will continue.
Landscape Restoration/Installation
Landscape restoration repair will take place in the Spring of 2024.
|