Strawberry Lane Road and Trail Project

May 18, 2023

Important takeaways from this message include:


  • Remaining tree removals and stump grinding is tentatively scheduled for early next week.
  • Storm sewer pipe from Smithtown Pond to Strawberry Lane is currently being installed and is anticipated to end at Strawberry Lane by the end of this week.
  • Xcel Energy and Mediacom are continuing their work on completing line relocations and power transfers this week through the end of May. Expect travel throughout neighborhood to be slow at times.
  • Throughout the next two weeks, silt fence will be installed and erosion control items will be installed to establish primary construction limits.
  • Equipment materials and supplies will continue be staged in various locations of the project site. We thank you for your patience with delivery crews and on-site contractors. 

Continue reading below, for more detailed information…


Remaining tree removals are planned to occur early next week. Remaining stumps will be ground out soon and remaining branches, sticks, etc. will be cleaned up prior to construction startup. This week and next week, Xcel Energy and Mediacom will be completing service installations and removing power poles. They will still be working in the roadway area at times. Please be patient, as travel through the neighborhood will be slow at times. Their work is anticipated to last until the end of next week.

 

In the next few weeks, the roadway contractor will be mobilizing equipment, materials, silt fence, and other miscellaneous items to the site. Please note that all supplies and equipment will be staged in the boulevard locations of the project area for the time being. Once the project begins, equipment and materials will be periodically installed and shifted around the site. If you are a resident traveling through the neighborhood, please be patient with delivery crews and contractors on-site. The resident project representative Tom Vidmar will be onsite periodically to introduce himself and begin helping coordinate construction activities. We ask that you please use this email update as a primary source of project schedule information and updates on major construction work to come. Tom will begin introducing himself to everyone along the project site next week. His contact info is listed below. Have a great weekend everyone!


Tom Vidmar

Design Engineer

Bolton & Menk Inc.

Cell: 612-578-2291

Email: [email protected]

The Strawberry Reconstruction Project was awarded by City Council on October 24, 2022. The first step of the construction phase will be tree clearing. City staff has been marking up the trees anticipated for removals with a dot of pink paint at the base of each tree. If residents have any questions on trees please contact City Engineer, Andrew Budde. The trees will later be marked with a large “X” a few days prior to the actual removal. It is anticipated that trees near the power poles will be trimmed for safety in the next few weeks. This trimming work will be done by Asplundh, coordinated by Xcel Energy. The full tree clearing work will be completed shortly following the trimming work. This clearing work will be done by Precision Landscape & Tree.


Proposed Schedule:


May thru September 2023: Construction


Please contact city hall if you have questions, 952.960.7900.


Project contacts:


Andrew Budde, City Engineer, 952.960.7910



Visit the Strawberry Lane project page
Facebook  Twitter  Instagram  Web

You are receiving this email because you are signed up for the Strawberry Lane, Smithtown Pond, and/or General Road Construction Updates eNews. To unsubscribe to all Shorewood emails, please select "Unsubscribe" below. To unsubscribe from this email only, or to update additional email requests, select "Update Profile". For assistance, contact the city at 952.960.7900, or reply to this email.