Project Related Topics
Completion Outlook
The Strawberry Lane Reconstruction Project was scheduled to begin in the Spring of 2023. Due to recurring scheduling conflicts on behalf of some of the private utility companies, construction startup was delayed almost 3 months. Currently, the construction project is behind schedule by about 6 weeks from the originally projected time of completion. Aside from just pavement and curb being installed, there are other construction activities that need to take place before the roadway can be open to through traffic. As roadway construction continues to progress, the roadway is scheduled to be open to traffic in October. Meanwhile, access will be restricted to local residents only.
Water Service Hook Ups
For those residents who are interested in the connection to City Water, please visit the city's website.
Turf Restoration
Turf restoration is scheduled to take place after the roadway is paved and general pavement and concrete repairs are completed. In the meantime, crews will be slowly excavating and removing miscellaneous debris and excess soils from the boulevard area as the road section construction is being completed. Turf seeding will take place this fall, but final turf seeding and touch ups will take place in the Spring of 2024.
Contractors will be responsible for watering lawns for 30 days, at which time residents will be notified that they are to take over maintenance (i.e. watering, mowing).
Tree Planting
Tree planting handouts will be provided in the coming weeks as the city is working on a supplier list of available trees for order.
Irrigation Repair
Irrigation repairs will come while topsoil and seeding preparation is taking place. This may happen sooner.
NEW info Sidewalk Installation
Sidewalk is still anticipated to be completed this fall. Driveway aprons adjacent to the sidewalk will be prioritized prior to the completion of the entire sidewalk.
|