Strawberry Lane Road and Trail Project

Strawberry Lane, Strawberry Court & Peach Circle Updates


September 11-15

On Monday, September 11 Roadway Section Construction Continues. Roadway section construction is scheduled to continue south of the intersection of Strawberry Court and Strawberry Lane and continue south into Peach Circle. Construction crews will be removing and reconstructing the road base a few hundred feet at a time each day. The area shown in RED will be the approximate working area for road section construction crews next week. Please keep in mind this may extend further south if crews are able to make significant progress. If you live in this area and need to leave throughout the day, please park your vehicles along Strawberry Court during the working hours of 7AM to 7PM next week. As road section construction continues, construction staff will coordinate with you for vehicle staging on a daily basis. Vehicle travel will be prohibited through the working area each day. Once the area between Strawberry Court, Peach Circle and the Minnetonka Regional Trail is completed, the roadway crews will begin constructing the roadway section south of the Regional Trail towards Alexander Lane. Driveway and resident vehicle access will be maintained outside the contractor working hours.


Residents living north of the working area are asked to utilize Smithtown Road as your primary neighborhood access point while construction crews are onsite during working hours next week.


Residents living to the south of the working area are asked to please utilize neighborhood access from Shorewood Oaks Drive or 62nd Street while crews are onsite next week.


All traffic on Smithtown Road will be maintained throughout the road section construction.

 

Please remind guests, visitors, or your contractors to travel slowly and cautiously through the site.

 

Reminders

Please remove any landscape items that you would like to save that are within the city Right of way area. 


Please label your garbage cans with your address written on duct tape so that crews may be able to move garbage and recycling cans for pickup on days where the roadway will not be passable. We ask that you set these cans out on Tuesday afternoon/evening so that crews can quickly move them to available pick-up locations outside of the working area.


Temporary mailboxes are installed and located along the North side of Shorewood Oaks Drive near the intersection of Strawberry Lane and Shorewood Oaks Drive. This includes mailboxes for all residents living on the Strawberry Lane project and adjacent roadways. To alleviate congestion, ensure mail delivery is not missed, and provide safety measures, it has been placed just outside of the construction. See the below image of the location:

If you have package deliveries that need to be made, please have them sent to City Hall to ensure safe keeping. Delivery drivers will not have access to the neighborhood while construction is taking place. The address is: Shorewood City Hall, 5755 Country Club Rd, Shorewood, MN 55331


Equipment, materials, and supplies will continue to be staged in various locations of the construction area. 

Resident Project Representative

 

Tom Vidmar

Bolton & Menk Inc.

612-578-2291

Tom.vidmar@bolton-menk.com

Visit the Strawberry Lane project page
Facebook  Twitter  Instagram  Web

You are receiving this email because you are signed up for the Strawberry Lane, Smithtown Pond, and/or General Road Construction Updates eNews. To unsubscribe to all Shorewood emails, please select "Unsubscribe" below. To unsubscribe from this email only, or to update additional email requests, select "Update Profile".


For assistance, contact the city at 952.960.7900, or reply to this email.