August 4
Storm Sewer Construction from Alexander Lane is scheduled to continue. If you work from home or need to leave throughout the day during these operations, you may be asked to park your vehicle outside of the day’s working area while crews are onsite. Construction staff will continue to help coordinate this with you. Please utilize the Cathcart Drive detour or utilize alternate routes accordingly. Residents living north of Alexander Lane, please utilize the north entrance of Strawberry Lane for access as crews continue to work south.
August 7-11
Storm sewer construction will continue from the Alexander Lane intersection and continue south towards 62nd Street. The resident project representatives will be coming around to help coordinate vehicle staging if necessary on a day-by-day basis. Please keep all personal vehicles out of the areas where crews are actively working.
Driveway removals for the remainder of the project south of Alexander Lane will take place early in the week. Please be patient with construction vehicles when traveling through the neighborhood.
A temporary water outage for residents on city water may be taking place for a day. The watermain construction and repair work for the existing system may be taking place in the intersection of Shorewood Oaks Drive and Strawberry Lane. Please be advised that the construction project representatives will be providing advanced notice to everyone affected in the area if this is scheduled to occur.
In the next few weeks
Roadway excavation and construction has been rescheduled a few weeks out. An update will be provided once the roadway construction schedule is confirmed.
The roadway contractor will be installing storm sewer, dropping off materials, and other miscellaneous items to the site. Trenches will be dug in the roadway, and equipment will be actively moving around onsite. Please note that all supplies and equipment will be staged in the boulevard locations of the project area during the end of each working day. If you are a resident traveling through the neighborhood; for your safety, please be patient with delivery crews and contractors on-site. The resident project representative Tom Vidmar will be onsite to help coordinate construction activities and communication with residents who will be affected on a day-by-day basis.
Please slow down
It has come to our attention that visitors, private residential contractors entering the neighborhood have been traveling at higher speeds through the construction zone. Please remind guests, visitors, or your contractors to travel slowly and cautiously through the site.
Please remove any landscape items that you would like to save that are within the city right-of-way area.
|