Construction Schedule Update: Aug 4-11

August 4

Storm Sewer Construction from Alexander Lane is scheduled to continue. If you work from home or need to leave throughout the day during these operations, you may be asked to park your vehicle outside of the day’s working area while crews are onsite. Construction staff will continue to help coordinate this with you. Please utilize the Cathcart Drive detour or utilize alternate routes accordingly. Residents living north of Alexander Lane, please utilize the north entrance of Strawberry Lane for access as crews continue to work south.


August 7-11

Storm sewer construction will continue from the Alexander Lane intersection and continue south towards 62nd Street. The resident project representatives will be coming around to help coordinate vehicle staging if necessary on a day-by-day basis. Please keep all personal vehicles out of the areas where crews are actively working.


Driveway removals for the remainder of the project south of Alexander Lane will take place early in the week. Please be patient with construction vehicles when traveling through the neighborhood.


A temporary water outage for residents on city water may be taking place for a day. The watermain construction and repair work for the existing system may be taking place in the intersection of Shorewood Oaks Drive and Strawberry Lane. Please be advised that the construction project representatives will be providing advanced notice to everyone affected in the area if this is scheduled to occur.


In the next few weeks

Roadway excavation and construction has been rescheduled a few weeks out. An update will be provided once the roadway construction schedule is confirmed.


The roadway contractor will be installing storm sewer, dropping off materials, and other miscellaneous items to the site. Trenches will be dug in the roadway, and equipment will be actively moving around onsite. Please note that all supplies and equipment will be staged in the boulevard locations of the project area during the end of each working day. If you are a resident traveling through the neighborhood; for your safety, please be patient with delivery crews and contractors on-site. The resident project representative Tom Vidmar will be onsite to help coordinate construction activities and communication with residents who will be affected on a day-by-day basis.


Please slow down

It has come to our attention that visitors, private residential contractors entering the neighborhood have been traveling at higher speeds through the construction zone. Please remind guests, visitors, or your contractors to travel slowly and cautiously through the site.


Please remove any landscape items that you would like to save that are within the city right-of-way area. 

Reminders


If you experience an internet outage, please report the outage to your provider prior to contacting the project representatives onsite.


Please label your garbage cans with your address written on duct tape so that crews may be able to move garbage and recycling cans for pickup on days where the roadway will not be passable. We ask that you set these cans out on Tuesday afternoon/evening so that crews can quickly move them to available pick-up locations outside of the working area.


Temporary mailboxes are installed and located along the North side of Shorewood Oaks Drive near the intersection of Strawberry Lane and Shorewood Oaks Drive. This includes mailboxes for all residents living on the Strawberry Lane project and adjacent roadways. To alleviate congestion, ensure mail delivery is not missed, and provide safety measures, it has been placed just outside of the construction. See the below image of the location:

If you have package deliveries that need to be made, please have them sent to City Hall to ensure safe keeping. Delivery drivers will not have access to the neighborhood while construction is taking place. The address is: Shorewood City Hall, 5755 Country Club Rd, Shorewood, MN 55331


Equipment, materials, and supplies will continue to be staged in various locations of the construction area. 

Resident Project Representative

 

Tom Vidmar

Bolton & Menk Inc.

612-578-2291

[email protected]

Visit the Strawberry Lane project page
Facebook  Twitter  Instagram  Web

You are receiving this email because you are signed up for the Strawberry Lane, Smithtown Pond, and/or General Road Construction Updates eNews. To unsubscribe to all Shorewood emails, please select "Unsubscribe" below. To unsubscribe from this email only, or to update additional email requests, select "Update Profile".


For assistance, contact the city at 952.960.7900, or reply to this email.