Street Repaving Update
The following streets are currently being repaved and are in various stages of completion:
North Park, Maple, Parkhill, Yellowstone, Northampton, Bayreuth, Hanover, Goodnor, Marlindale, and Euclid Heights Boulevard (eastbound only, began 7/26).
We anticipate work will be about 90% complete by August 15, weather permitting.
Final paving has occurred on North Park, East Scarborough, Kingston, Maple, Parkhill, Whitby, Bayreuth, and Yellowstone.
Road Construction Alert: Yellowstone Road (Noble to Monticello)
Residents of Yellowstone, please be advised that road construction crews are installing concrete driveway aprons, rendering driveway access to homes temporarily out of service until Monday, August 18th.
Residents, please plan to park your vehicle on the street overnight. On-street parking is being permitted to allow the concrete the proper time to cure. After curbs and aprons are installed, crews will begin resurfacing the street starting on August 15. The surface course will be installed the week of August 25. All vehicles must be removed from the street by 7 am to ensure work can continue.
No thru traffic will be permitted on Yellowstone until after the week of August 25, 2025.
East Fairfax (Lee to Taylor)
Road work is scheduled to start on August 11, weather permitting. Crews will install new curbs and partial aprons on the north side of Fairfax and conduct repairs on the south side of the street.
Residents, please note:
· Street parking is prohibited after 7 am
· Follow posted signs and construction notices from the contractor
· Trash pickup will take place from 6 - 7 am [place items out by 6 am]
· The estimated completion time is 3 - 4 weeks, weather permitting.
Euclid Heights Boulevard (Eastbound)
Repaving between Cedar Glen and Coventry began July 26. Expect intermittent closures and delays. Residents will retain driveway access at the end of each workday.
The base course has been installed, and the casting adjustment is underway.
Trash collection: 6–7 am—please place items on the tree lawn by 6 am.
Estimated completion: 2 weeks, weather permitting.
Bellfield Avenue Valve Replacement (Cleveland Water)
Fabrizi Trucking & Paving will perform valve replacements July 28–August 15. Apron work is in progress at various locations. Residents, please plan to park your vehicle on the street overnight. On-street parking is being permitted to allow the concrete the proper time to cure.
No street parking after 7 am
Follow posted signage
Trash pickup: 6–7 am—place items out by 6 am
Estimated completion: August 15, weather permitting.
|