Phase 1 | September 2025
-
Location: W 27 Street between Lake Avenue and Sunset Drive between and W 27 Street and W 25 Street (Sunset Islands II).
-
Scope: Underground sewer pipe will be installed using a low-impact drilling method. Please know that the contractor will revisit this phase to finalize the pipe connections. This process will take place after Phase 4 is completed as part of a phased approach.
Phase 2 | September 2025
-
Location: W 27 Street and Lake Avenue, W 23 Street and Lake Avenue, W 23 Street between Bay Avenue and Sunset Drive (Sunset Islands II & III).
-
Scope: Sewer pipeline will be installed beneath the water using a low-impact drilling method. Equipment will be placed on Sunset Islands II near W 27 Street and Lake Avenue, with the pipe exiting on Sunset Islands III, north of W 23 Street and Lake Avenue. Please know that the contractor will revisit this phase to finalize the pipe connections. This process will take place after Phase 4 is completed as part of a phased approach
Phase 3 | October 2025
-
Location: W 25 Street and Lake Avenue, W 24 Street and Lake Avenue, and W 23 Street between Bay Avenue and Sunset Drive (Sunset Islands II & III).
-
Scope: Underground water main will be installed beneath the water using a low-impact drilling method. Equipment will be placed on Sunset Islands II, south of W 27 Street on the west side of Lake Avenue. The pipe will exit on Sunset Islands III, with a work zone along the south side of W 24 Street and Lake Avenue. Please know that the contractor will revisit this phase to finalize the pipe connections. This process will take place after Phase 4 is completed as part of a phased approach.
Phase 4 | October – November 2025
-
Location: W 23 Street and Lake Avenue and W 23 Street between Bay Avenue and Sunset Drive (Sunset Islands II & III).
-
Scope: Underground water main will be installed beneath the water using a low-impact drilling method. Equipment will be placed on Sunset Islands II, south of W 27 Street on the west side of Lake Avenue. The pipe will exit on Sunset Islands III, with sections placed along the north side of W 23 Street and Lake Avenue. Please know that the contractor will revisit this phase to finalize the pipe connections. This process will take place after Phase 4 is completed as part of a phased approach.
Phase 5 | November – December 2025
-
Location: Sunset Island III entrance on Sunset Drive and W 23 Street and Lake Avenue.
-
Scope: Underground sewer main will be installed and connected along Sunset Drive near the entrance of Sunset Islands III, with additional open trenches between drilling sites at W 23 Street and Lake Avenue in the swale area.
Phase 6 | December 2025 – January 2026
-
Location: Sunset Island II entrance on Sunset Drive and W 27 Street and Lake Avenue.
-
Scope: Underground sewer main will be installed and connected along Sunset Drive near the entrance of Sunset Islands II, with additional open trenches between drilling sites at W 27 Street and Lake Avenue in the swale area.
Timeline
The contractor is scheduled to mobilize to the site on Monday, September 8, 2025, to begin locating utilities. The project is expected to span approximately seven (7) months, including full restoration of the project area upon completion. Approved construction hours are Monday through Friday, 8 a.m. to 5 p.m. Any additional work hours will require prior approval and community notification.
Please note that the schedule may be subject to change due to weather conditions or other unforeseen factors.
Roadway Impacts
Traffic management and lane changes for Phase 1 are outlined below. Lane closures and additional details for the five (5) remaining phases will be provided in future advisories.
|