Franklin Street Bridge Project
CDOT crews began sidewalk replacement and selective roadway grating replacement at the Franklin Avenue Bascule Bridge over the Main Branch of the Chicago River.
Scope of Work:
The project consists of performing the following repairs: replacement of bridge sidewalk with fiberglass sidewalk panels, selective roadway grating panels replacement.
Construction Schedule:
7:00 am - 3:00 pm, Monday thru Friday, from Monday, March 18th until Friday, August 30th. End date is tentative, contingent upon expected Central Business District Moratoriums.
Traffic Impact during Construction:
- Full closure of one sidewalk at all times.
- A single vehicular lane closure adjacent to the sidewalk being worked on at all times.
- One northbound though lane and northbound bike lane will remain open throughout during sidewalk repairs.
Crane Lift: 40 East Erie Street
Stevenson Crane will conduct a crane lift at 40 East Erie Street on Wednesday, March 27, from 9am to 4pm.
During the lift, the following will be closed:
- Sidewalk on the north side of Erie, from Wabash to a point 100' east thereof
- Curb lane on the north side of Erie, from Wabash to a point 100' east thereof
- Two traffic lanes on Erie, from Wabash to a point 100' east there of
The curb lane on the south side of the street will be converted into an eastbound traffic lane during the lift.
Crane Lift: 400 W Ontario
On Friday, April 5th at 9am to Sunday, April 7 at 8pm, there will be a crane lift at 400 West Ontario Street. Throughout the lift, westbound traffic on West Ontario, from North Orleans to North Kingsbury will be prohibited.
Filming
Chicago Fire
Chicago Fire is scheduled to film at 222 W Ontario on March 26 from 5:30 am – 3:30 pm. Parking will be prohibited at the following locations:
- North side of Ontario from Franklin to Wells (March 25, from 7am to 5pm)
- East side of Franklin from Ontario to Erie (March 25, from 7am to 5pm)
- East side of Franklin from Ontario to Erie (March 25, from 7am to 5pm)
- North side of Ontario from Franklin to Wells (unloading only) (March 25, from 7am to 5pm)
- South side of Erie from Franklin to Wells (March 25, from 7am to 5pm)
If you have any questions or concerns, please contact Will Higgins (773) 525-2326.
Loews Chicago Hotel
On Monday, March 25th, a commercial will be filming interior scenes at Loews Chicago Hotel, 455 N Park Dr. During filming parking will be prohibited at the following locations:
-
East Side of Park Dr from Illinois St to North Water (Monday, March 25: From 5:00AM to 8:00PM)
-
West Side of New St from Illinois St to Lower North Water (Monday, March 25: From 5:00AM to 8:00PM)
-
South Side of Lower North Water from McClurg Ct to Columbus Dr (Monday, March 25: From 5:00AM to 8:00PM)
If you have any questions or concerns, please contact Larry Versola, Location Manager, 312.925.5638.
Kubelik
Minim Productions, Inc will be filming scenes for the TV Show titled “Kubelik” in your neighborhood on Saturday March 23, 2024. In order to park essential vehicles and equipment, parking will be prohibited at the following locations:
-
Both Sides of Superior St from Orleans St to Wells St Saturday March 23, 2024 (8AM - 11:45PM)
-
South Side of Chicago Ave from Orleans St to Wells St Saturday March 23, 2024 (8AM - 11:45PM)
-
Both Sides of Franklin St from Chicago Ave to Superior St Saturday March 23, 2024 (8AM - 11:45PM)
If you have any questions, concerns or special needs, please contact Maria C. Roxas at (312)282-0283
EOOP
On Monday, March 25th, "EOOP" will be filming dialogue scenes inside 160 N LaSalle and City Hall in the evening. During filing, prep, and wrap, parking will be prohibited at the following locations:
-
Sunday, March 24: From 8:00PM to Monday, March 25th at 11:59PM
- Both Sides of Lake St from Wacker Dr to Wells St
- East Side of Clark St from Washington to Madison
If you have any questions or concerns, please contact Jon Klemke, Asst. Location Manager, 312.209.8352.
Indie Film
On Friday, March 22nd, "Where's George?" will be filming dialogue scenes inside and outside Assumption Church. 323 W Illinois St. During filing, prep, and wrap, parking will be prohibited at the following locations:
- Friday, March 22: From 9:00AM to 11:00PM
- South Side of Illinois from Franklin to Orleans
- West Side of Franklin from Illinois south to the alley
If you have any questions or concerns, please contact Grace Schuler, 330.272.8518.
Lake Shore Drive Bridge Repairs
Bridge Repairs have began on the Upper level of DuSable Lake Shore Drive Bascule Bridge over the Main Branch of the Chicago River.
This work is separate from the ongoing Pin & Link work at the bridge and will not impact that construction, or require additional roadway closures. Details of the temporary sidewalk restrictions are below:
Scope of Work:
The work consists of upper level stringer repairs at the SE and NE bridge houses.
Construction Schedule:
-
8:00 pm - 6:00 am Sunday, March 10th 2024 until Thursday, March 28th 2024.
- Work will occur on Sunday nights - Thursday nights only. No work to occur on Friday nights or Saturday nights.
Traffic Impact during Construction:
- The east sidewalk and bike path will be reduced to a shared travel lane in both directions during working hours.
- The east sidewalk and bike path will be completely open to pedestrians and bicyclists during non-working hours.
- This work will not impact the ongoing Pin & Link construction or cause additional road closures.
- The west sidewalk will remain completely open to pedestrian traffic at all times.
CDOT Construction: Pin & Link Plate Assembly and Expansion Joints
The Department of Transportation will begin a project to replace pin and link plate assemblies and expansion joints associated with the bridge structures of upper and intermediate Columbus Dr., Randolph St., and Stetson Ave. Pin and link plate assembly work will be performed from the underside of the bridge decks while expansion joint replacements will occur from above. The work began in November 2023 and will progress to completion (anticipated Fall 2024).
Work is to start along upper, intermediate, and lower levels of the following roadways:
- N. Columbus Drive between E. Wacker Drive and E. Randolph Street
- E. Randolph Street between N. Michigan Avenue and N. Field Boulevard
- N. Stetson Avenue between E. Wacker Drive and E. Lake Street
During construction, portions of these bridge structures will be barricaded off to prohibit vehicles and pedestrians directly over the active work.
- Vehicles will be shifted and/or detoured to allow the work to progress.
- The sidewalk on at least one side of the roadway and crosswalks at roadway intersections will remain open for pedestrians.
- Coordination of temporary access restriction may be required with private properties directly adjacent to the project.
Murphy Auditorium Renovation
Driehaus Museum purchased the Murphy Auditorium (50 E Erie) in June 2023, and began the following interior renovations:
- Offices are going to be renovated
- Stage has sunken – leveled out; fix accessibility issue
- New elevator to go all the way to the top floor
Throughout the project, the following will be in-place:
- Pedestrian canopy over the sidewalk in front of 50 E Erie
- 100' of curb lane will be closed in front of 50 E Erie for material deliveries and small crane
They will need to use a small crane periodically throughout the project to lift materials onto the roof that can't fit through the doorway.
LSD Bridge & Viaduct Project - September 25 to Summer 2024
The Chicago Department of Transportation (CDOT) began working on the Lake Shore Drive Bridge and Viaduct Network between Monroe and Ontario. This work will include removing and replacing link plates, stainless steel pins, and Teflon bushings and expansion joint rehabilitation.
Upper Level Lake Shore Drive will have one permanent lane closure in each direction and an additional lane closure during off-peak hours.
Intermediate Level Lake Shore Drive will have two permanent lane closures in each direction.
This project is expected to be completed summer of 2024.
Temporary Bus Stop Elimination
Until March 2024, the westbound bus stop at Grand and St. Clair will be temporarily removed.
- Stop ID Number: 761
- Route Stopping: #29 – State, #65 – Grand, #120 – Ogilvie/Streeterville Express, #121 – Union/Streeterville Express
State & Lake Utility Relocations
Utility companies began relocating utilities in advance of the State and Lake CTA project. Train services will not be disrupted during utility relocations.
At least 1 lane of traffic will remain open (1 lane each direction on State St) at all times, but other driving and parking lanes may be closed.
Construction equipment and materials will be stored on the street, including during time periods between active work. Work will primarily occur 9:00 AM to 4:00 PM on weekdays and 8:00 AM to 8:00 PM on Saturdays, but there will be limited work during nights. Utility companies are aware of and required to abide by the Chicago noise ordinance, which limits noisy work during overnight hours.
Kennedy Expressway Bridge Rehabilitation
In 2023, IDOT began rehabilitating the Kennedy Expressway (Interstate 90/94), from the Edens Expressway (I-94) junction to Ohio Street.
The estimated $150 million project consists of rehabilitating 36 bridges and the Reversible Lane Access Control system, replacing overhead sign structures, installing new signage and modernized LED lights, pavement patching, and structural painting. Additionally, Hubbard’s Cave, from Grand Avenue to Wayman Street, will be painted and new LED lighting installed.
The work will take place over three consecutive construction seasons, broken down into the following stages:
-
2023 – Inbound Kennedy: Click here for stage 1 fact sheet.
-
2024 – Reversible Express Lanes: Click here for stage 2 fact sheet.
-
2025 – Outbound Kennedy: Click here for stage 3 fact sheet.
The Kennedy Expressway officially opened in November 1960, with the last major rehabilitation completed in 1994. The project will improve safety, traffic flow and reliability for the more than 275,000 motorists who use the expressway each day.
Click here for a project overview.
Click here for a FAQ
Click here to see photos and videos of the project.
|