W Building Construction Project Update
Week of July 29
Next week crews will continue building Air Handling Unit 2 and installing duct work. Crews also will be installing steam piping, chilled water piping and hot water piping in the mechanical penthouse. The impact to occupants should be low. If you have questions, comments or concerns, please contact Dylan McIntosh.
|