W Building Construction Project Update
Week of June 3
Next week, crews will continue building Air Handler 3 (AHU-3) and the Exhaust Air Handling Unit. Additionally, crews will continue to install drain piping, control wiring and duct work in the penthouse and roof. Crews also will be starting the demolition of select parts for Air Handler 2 (AHU-2). Occupants should expect impact to be low for the week.
If you have questions, comments or concerns, please contact Dylan McIntosh.
|