There is an upcoming road closure mid-March in downtown Leavenworth to accommodate a sewer mainline replacement effort which will be completed over a two-week period. The following street(s) will be impacted:
Week One
Closure Dates: Monday, March 18, 2024 – Friday, March 22, 2024
Closure Hours: 7am to 6pm
9th Street between US Hwy 2/Front Street and Commercial Street
Traffic Restrictions:
- No vehicle traffic allowed except for Emergency Vehicles; An emergency vehicle lane will be provided; Contractor will set detour signs and alternate hospital route.
Parking Restrictions:
-
There will be no parking allowed on 9th Street between Front Street and Commercial Street during the entirety of this week, regardless of working hours.
Pedestrian Access:
-
Allowed on the west side of 9th Street, only.
Edelweiss Weg Alley between 9th and 10th
Traffic Restrictions:
- No vehicle traffic allowed; Alley deliveries will be impacted during working hours.
Week Two
Closure Dates: Tuesday, March 26, 2024 – Friday, March 29, 2024
Closure Hours: 7am to 6pm; w/ overnight work starting at 9pm on Tue., 3/26 until 12pm on Wed., 3/27
Edelweiss Weg Alley between 9th and 10th
Traffic Restrictions:
- No vehicle traffic allowed; Alley deliveries will be impacted during working hours and overnight work.
Please plan accordingly during these weeks of upcoming construction downtown. NOTE: Closure dates and/or locations are subject to change to accommodate work.
|