An important part of Wallworks’ scope of work was the exterior radius walls that form the hitting bays and interior framing. To accommodate the aggressive schedule, Wallworks used a pre-fabrication process to complete this work.
“Because of the large, 600-foot radius of the walls, layout of the walls would have required our surveyor to have unobstructed access to large parts of the project", says Project Superintendent, Rob Thorne. “With so many trades working at on the project during this time, this would have been impossible without delaying their work."
To address this, Wallworks engaged Radius Track to provide prefabricated, curved, cold-formed steel tracks. Shop drawings produced from the construction documents led to Radius Track producing pre-bent tracks off-site. "Each piece of track was individually numbered to match the location provided on the shop drawings", says Rob. The prefabricated framing process is an economical, duplicate-able process that ensures geometrically-precise curved walls.
For the Top-Golf project with stringent quality requirements, ensuring tight QA/QC is an important success factor for the Wallworks Team.