UPDATE for DELTA BRIDGES CONSTRUCTION:
Rio Vista Bridge
The Lift Span Deck Replacement has been completed, however, there are still items of work remaining. Motorists should expect single lane reversing traffic control through the year.
Paintersville Bridge
Work is on schedule to have the bridge back in service on July 31 as planned.
These delta bridges were originally constructed in the early 1920s and then reconstructed or refurbished in the early 1950s. Repair work is required to ensure the safety of the structures.
Weather conditions could delay or cancel scheduled work. Caltrans advises motorists to “Be Work Zone Alert.” For motorists using the State Route 84 Real McCoy and State Route 220 Ryer Island ferries as a bridge detour, additional ferry information is located at Delta Ferries | Caltrans or call the Caltrans Ferry Update Line at (510) 622-0120 for the latest information.
Bay Area motorists can check 511.org: https://twitter.com/511SFBAY or follow Caltrans District 4 on X at: x.com/CaltransD4.
Caltrans District 3 is responsible for maintaining and operating 4,385 lane miles in 11 Sacramento Valley and Northern Sierra counties. Caltrans reminds motorists to “Be Work Zone Alert” and slow in construction zones for the safety of travelers and crews performing these improvements.
Caltrans issues construction and road condition updates on X @CaltransDist3 and on Facebook at CaltransDistrict3. For real-time traffic information, click on Caltrans’ QuickMap quickmap.dot.ca.gov/ or download the QuickMap app from the App Store or Google Play.
|