LINDNER CENTER OF HOPE - MARCH 2026

Beacon Update

Bridge Update: A Path to Hope and Healing!

The pedestrian bridge is complete and has passed inspection!



Crews are now working on connecting pathways and finishing electrical work for lighting and cameras. Concrete paths will be completed as soon as weather allows.



A huge thank you to our generous donors, hardworking crews, and supportive staff and community, together, we’ve built a Path to Hope and Healing for everyone!

Campus Construction Update

Recent heavy rain has slowed progress on the Medical Office Building. We appreciate the patience of our staff, patients, and visitors as crews wait for safe conditions to resume.

Medical Office Building (MOB)

  • As soon as the weather permits, they will continue working on the concrete footings for the foundation of the building.
  • Steel will start being delivered to the site. They anticipate steel work to commence the week of March 23.

Parking & Access

  • Handicap parking spots by the Welcome Center are delayed due to the significant amount of rain. The spots will be completed when weather permits.

Sibcy House Addition

  • Connection of the new 8-bed wing to the current Sibcy House will begin the week of March 9.

We’re grateful for everyone’s patience as we work to enhance our campus for greater healing, comfort, and accessibility. More updates will be shared as progress continues.