Medical Office Building (MOB) & East Side Work:
Construction on the new Medical Office Building continues to progress. The gas line adjacent to the future foundation must be relocated, which has created some delays and will also postpone the closure of Lot A. In addition, engineers are evaluating a large concrete slab discovered at the site to determine its impact on the foundation of the new structure. We expect to resume work soon. Once the piers and piles are installed, steel is waiting offsite to be delivered. We’re hopeful to see steady and visible progress on the MOB very soon.
Sibcy House: Installation of underground utilities is underway, with completion expected later this month. Once that work is finished, visible structural progress will begin to move more quickly.
New Parking Lot: Sidewalks and curbs are being installed.
Fire hydrants have been placed. Electric work is underway.
Gravel installation is expected to begin this week. The goal is to have the new parking lot completed and ready for use by October 31.
We appreciate your continued patience and flexibility as construction progresses. Each step brings us closer to expanding our capacity to serve patients and families and advancing the mission of Lindner Center of Hope.
|