VIRGINIA BEACH – As progress continues on the I-64/I-264 Interchange Improvements Project, a series of ramp and lane closures will be in place next weekend, allowing crews to safely perform bridge work.
Due to the nature and scope of this work, motorists are encouraged to prepare for delays and seek alternate routes, when possible. Plan your commute with VDOT’s free traffic information tools:
-
Follow @VaDOTHR on Twitter
-
Download the 511 smartphone app or 511-integrated Waze app.
-
Visit the 511Virginia website or dial 511 for traffic information on your phone
The following work is weather-dependent, and the schedule is subject to change.
Multiple Lanes Closed on I-264 East, With Ramp Closures Also Scheduled
Beginning as early as 7 p.m. on Nov. 12 and continuing through 5 a.m. on Nov. 15, crews will implement a series of progressive, multi-lane and ramp closures on I-264 east for milling and concrete work on the I-264 bridge just west of the Witchduck Road interchange.
To help facilitate this work, the following ramps will be closed:
- The flyover ramp from I-64 west to I-264 east (inside set) (exit 284B) continuously from Nov. 12 at 7 p.m. through Nov. 15 at 5 a.m.
- The ramp from I-64 east to I-264 east (exit 284A) Nov. 12-14 from 10 p.m. until as late as 8 a.m.
- The 64 Express Lanes Nov. 12-13 from 7 p.m. until as late as 11 a.m.
The I-64 ramps to the collector-distributor road (I-64 west to Newtown Road, exit 284B) will remain open to traffic.
Beginning as early as 10 p.m. on Nov. 12-13, mainline I-264 (inside set) will close to all traffic between approximately Military Highway (exit 13) and Witchduck Road (exit 16), with all eastbound motorists shifted to the collector-distributor road (outside set) during this time to get around the bridge work.
The eastbound collector-distributor road will be reduced to one lane Nov. 12-13 as early as 10 p.m. until as late as 6 a.m. Slow rolls with stoppages of up to 20 minutes on I-264 east are scheduled to occur on Nov. 12 as early as 10 p.m., as well as on Nov. 15 from 2-5 a.m.
Starting as late as 8 a.m. on Nov. 13-14, mainline I-264 east (inside set) will reopen to traffic, with three through lanes open to traffic. Two center lanes on I-264 east, just before the Witchduck Road (exit 16) interchange will be closed to traffic. The center, double-lane closure will leave two right lanes and one left lane open to traffic while the work is underway. Signs will direct all I-264 east traffic heading to Witchduck Road (exit 16) to utilize the collector-distributor road.
This lane/ramp closure schedule and traffic pattern was previously implemented Oct. 22-25.