The majority of work will be done at night to reduce traffic jams. However, there will be some daytime work too, but this shouldn't impact traffic.
- Traffic signal bases and electric conduit are being placed along the eastbound shoulder
- We continue excavation work and placing road base materials along the eastbound shoulder between
- I-15 and Center Street.
- Nightly work Sunday through Thursday nights 7 p.m. - 6 a.m.
Traffic Impacts:
- All traffic lanes will temporarily shift to the north on US-6.
- The trail along US-6 is now closed for the duration of the project. Trail users may encounter other temporary closures of sidewalks in the area. Please follow the indicated detours for your safety. Accessibility under the Americans with Disabilities Act (ADA) will be maintained.
- Business access will remain open.
Enhancements include:
- Implementing dual left turns at Expressway Lane and Canyon Creek Parkway.
- Adding a third eastbound lane, extending to the east of Expressway Lane.
- Installing new asphalt paving from I-15 to the mouth of Spanish Fork Canyon.
- Relocating the trail on the south side of US-6.
These improvements are designed to enhance traffic flow, safety, and overall connectivity in the area.
|