TRAFFIC ALERT: WEEKEND INTERSECTION IMPACTS
Dates:
- Friday, August 23 at 8 p.m. to Monday, August 26 at 6 a.m.**
Details:
-
We will be working in the center lanes of the Expressway Lane/800 North Intersection on US-6. Traffic will be in a temporary traffic configuration with two lanes eastbound and a single lane westbound at the intersection of Expressway Lane/800 North. NO CROSS TRAFFIC from side streets will be allowed.
- Lane closures will be in place around the clock from Friday, August 23 at 8 p.m. through Monday, August 26 at 6 a.m.**
- Expect major delays.
- PLEASE FOLLOW POSTED DETOURS
**The specified pavement thickness is 12". Before the intersection can be opened, the asphalt pavement must cool down. Due to the thickness of the pavement section, opening may be delayed.
We will be applying water to the new asphalt during the day on Sunday to help cool the pavement to acceptable temperature. Water will be present on the open lanes of traffic.
|