Capital Campaign Update
First things First - Many thanks to the newer member who donated $3,000.00 to our Capital Campaign recently. They were not an active member when we held the campaign. We appreciate their generosity.
August 2025 Capital Campaign (CC)’22 Status Summary:
The monthly CC Status Summary Spreadsheet shows the prioritized project list, our initial estimated cost of each project, actual contractor quotes we have received for the work and much more.
This is the first eNews CC’22 Status Summary since March 2025. In the last few months we have continued to push for completion of the on-going projects. Namely – the Memorial Walls, stormwater improvements, additional solar panels, and the design of the Air Conditioning (AC) project. The AC project is the largest cost project in the CC. We are hopeful that we will be able to get drawings soon and bids from contractors this fall. As mentioned at the annual congregational meeting in June, we have been wary of moving forward with too many other projects until we have a handle on the AC cost, hence there has been reduced spending of CC funds recently.
Please click this link to review the latest CC Status Summary Spreadsheet update.
We are still working on several projects other than the AC. Just this past week we engaged Pittsburgh Asphalt Company to pave our driveway at a cost under our estimate. We had hoped to renew all of our paved surfaces but ultimately, with the AC cost still unknown, decided to do only the work promised in the Enhanced Plan.
We are trying to self-perform as much of the work as possible. Anyone with a desire to lend a hand is welcome to contact Joe Meier (see below). People with electrical wiring or carpentry skills would be especially welcome. Any questions or offers of help can be sent to Joe.
|