Update: Collins Canal Water Main Improvements

Notice Date: Thursday, October 22, 2026

What's Happening?

The contractor has successfully completed all water main improvements. Remaining activities include roadway resurfacing, pavement striping and restoration of the entire project area to its pre‑construction condition.


Beginning October 26 and continuing through November 2, 2026, the contractor will mill and resurface the roadway at multiple locations simultaneously. Roadway milling is expected to take approximately one day to complete, followed by roadway resurfacing and temporary striping, which will take an additional 2–3 days across all areas. Below is a list of each activity and the associated traffic impacts:

Location

Scope

Traffic Impacts

23 Street between Liberty Avenue and Park Avenue

Roadway milling and resurfacing

Both the westbound and eastbound lanes will be temporarily closed as work progresses. Access to properties will be maintained at all times.

22 Street between Park Avenue and Washington Court

Roadway milling and resurfacing

Westbound lane will be temporarily closed as work progresses. Access to properties will be maintained at all times.

Dade Boulevard (near Miami Beach Senior High School)

Roadway milling and resurfacing

South, westbound lanes will be temporarily closed as work progresses. Access to properties will be maintained at all times.

Upcoming Activities

Permanent pavement striping is anticipated to begin the week of November 16–20, 2026, followed by final restoration of the entire project site to its pre‑construction condition.


Timeline

Work hours are Monday through Friday from 8 a.m. to 8 p.m. Please know that this project is anticipated to be completed by Fall 2026, barring any unforeseen delays or circumstances.


What to Expect

  • Temporary lane closures and traffic control measures will be implemented as necessary to safely accommodate the work.
  • All closures will be temporary and limited to the duration of active construction operations and impacts will be intermittent throughout the week as crews progress through each work area.
  • Moderate levels of construction noise are expected during work activities.
  • Partial sidewalk closures throughout the construction zone will be in place. Please follow all posted signage.
  • Access to the Valero gas station will be maintained at all times.
  • Select parking spaces adjacent to each work zone will be temporarily unavailable.
  • Machinery and workers will be present on the job site. Residents and visitors are advised to use caution when crews are present and to follow all posted signage.

Contact

To explore the project’s history and previous updates, please visit our project page for more details.


For more information, please contact the Mid Beach Neighborhood Affairs Coordinator Gabriella Gonzalez at GabriellaGonzalez@miamibeachfl.gov.

To learn more about the city’s projects and innovative initiatives, visit www.miamibeachfl.gov/NAD.


To request this material in alternate format, sign language interpreter (5-day notice required), information on access for persons with disabilities, and/or any accommodation to review any document or participate in any city-sponsored proceedings, call 305.604.2ADA (2232) (voice), select 1 (English) or 2 (Spanish) and leave a message with your request. TTY users may call via 711 (Florida Relay Service). You can also make requests online at www.miamibeachfl.gov/ada by selecting ADA request.