Here is the March 14th update on the reconstruction:

December & January-


  • 3D scanning technology identified all water affected areas of the church building.
  • City inspectors gave their reports and permits were issued. 
  • Damaged flooring removed in the West End Hallway, Office Copy Room, West End kitchen and Family Life Center.
  • Damaged drywall removed.
  • Industrial fans and dehumidifiers utilized for several days to ensure complete water extraction.

February & March-


  1. Vinyl tile flooring installed in the Office Copy Room and the West End kitchen.
  2. Drywall installed and all finish coats of drywall compound sanded in the West End Office area and West End Hallway.
  3. Painting completed in the West End Hallway.
  4. Asbestos remediated in the Narthex area and both Hallways on either side of the Sanctuary (the original first floor hallways).
  5. Hallway floors are currently UNFINISHED but will be carpeted very soon.
  6. They are starting the flooring in the Family Life Center.
  7. The building is now open, but we are urging caution as the building is still under reconstruction.
  8. The office area will still be temporarily located on the East End.

Thank you for your prayers, patience and support!