The Diversion Board of Authority accepted a new cost estimate and adjusted funding plans for the project and endorsed the proposed funding approach.

After reviewing the updated costs from 2015 dollars to 2018 dollars, design changes from Plan B, modifications to utility relocates along the channel and revised contingencies, the total project is now estimated to cost $2.75 billion in 2018 dollars. The costs are based on the project submitted to the MDNR and is subject to revisions once final approvals are obtained. With the approximately $430 million works completed to date, $2.33 billion in project costs remain. Read More
FM Area Diversion Project
Flood Diversion Authority
 Box 2806, 211 Ninth Street South, Fargo, ND 58108  
Learn more about the FM Area Diversion Project at www.fmdiversion.com