Work in preparation for the UV pilot program is ongoing and will continue the week of May 26th.
The following work is planned:
- Installation of weir plates in culvert and completion of final connections between pumps and UV unit
- Full scale startup and commissioning of UV Pilot projected to begin on Wednesday, May 28th and last through Friday, May 30th
- Preliminary sampling to begin on Friday, May 30th
During all times that contractors are working in the roadway, police detailing will be requested and traffic control signage will be employed to minimize disruption to traffic throughout the area. At various times, temporary detours will be required to facilitate the work. All construction activity will occur between the hours of 9:00am and 4:00pm.
|