Upper Kirby District Street Talk  

Join Our Mailing List         Like us on Facebook  Follow us on Twitter
In This Issue:
District Roadway Construction
METRO Summer Fun Pass
Upper Kirby Conference Center Now Open
Upper Kirby at Work

Before


Join Our Mailing List
After
levyparkhouston.com
Community Resources:
Visit levyparkhouston.org for more information.

               Upper Kirby Update  Like us on Facebook Follow us on Twitter 

June 2, 2017

Upper Kirby Construction
Final Section of the Northern Half of Westheimer Underway
                       Roadway Demolition Underway
Westheimer Reconstruction: 
Kirby to Buffalo Speedway
 
Crews are now working on the north side of Westheimer between Eastside and just west of River Oaks Boulevard. Over the last week, they have continued demolition efforts and have progressed both storm sewer and water line installation. This activity will likely continue for two to three more weeks, at which point, pavement preparation and placement can take place. The goal is to complete lanes and driveways on the north side of the street by mid-July and shift pavement efforts to the south side of Westheimer. 

Crews have nearly completed pavement work on Sackett on the east side of the street and have been working to construct the storm sewer inlet leads to the west side of the street. This work will continue next week. Storm work on Elbert and the restoration of the Philfall/ Sackett intersection still remains on this piece of the project. Once all underground work has been completed, workers will overlay the entire roadway. During construction, two-way traffic will be maintained, although on street parking will not be available. 

Westheimer Reconstruction:
Kirby to Shepherd

Upper Kirby work on Westheimer between Kirby and Shepherd has been substantially complete since February, 2016 and has been awaiting removal of overhead utilities by various telecommunications companies prior to finalizing the back of curb area. 

Several trees installed did not survive installation and the contractor has been working to secure matching replacements. Tree work is scheduled for mid June and will include limbing up of healthy trees to better clear the pedestrian path. 

Lines were finally removed May 11th and 12th. Once CenterPoint Energy removes the poles, the back of curb area will be restored.  
A Westheimer Free of Overhead Power

Comcast is the sole utility on the poles remaining between Kirby and Buffalo Speedway. Comcast has indicated that work would be completed late this month. Look for further updates as this work progresses. 

Bissonnet Reconstruction:
Kirby to Buffalo Speedway

Work on Bissonnet between Kirby and Buffalo Speedway was stopped late last year due to a contractor dispute. Work began between the Kirby intersection and Dincans on the north side of the street. Upper Kirby retained a second contractor to complete work on this area. This contractor completed this work just prior to the holidays. The remainder of the work has been repackaged for a new bid. The project will be bid in June with construction  likely   beginning in July. 
  
For more information on Upper Kirby construction and related activities or for construction related issues or concerns, please contact Travis Younkin at 713.524.8000 or  [email protected].   

METRO Summer Fun Pass
    


Upper Kirby Conference Center
    

Upper Kirby's Conference Cente r is centrally locat ed and easily accessible  from US 59 and Kirby Dr. in the hear t of Houston. 

Ideal for hosting your organization's seminars, meetings or social events.
 42' x 26' Room (1,092 sf.)
  •  Exterior door accessible after business 

  • hours and on weekends
  •  Wi-Fi / Internet Accessible
  •  75" television/projection screen
  •  Kitchenette with sink, coffee maker, ice maker an
  • d microwave oven
  •  Ten - 6' x 2' collapsible conference tables
  •  Large Conference table - 18' x 4 ½ 'OR can be reconfigured to:
1 (One) -55" x 55" round table and
3 (three) -55" x 55" square tables
  •  18 - Conference chairs
  •  40 - Stackable chairs
  •  Credenza
Room accommodates 75-100 guests standing  buffet reception style set-up.
 
For more information, contact  Linda Gilliam at 713.524.8000 or  [email protected]
 

If you have a new business, development or community event that you would like included in the monthly Upper Kirby news, please contact us at 713.524.8000 or submit to [email protected]
 
Requests will be posted subject to space availability and appropriateness of content.


Photo Credit: Morris Malakoff 
courtesy of Levy Park Conservancy
Upper Kirby is a constantly evolving urban area marked by an outstanding location, great shopping, unique residential neighborhoods, smart development and a small town feel. It is an area of successful businesses, involved communities and a synergy between the public and private sectors. It is the heartbeat of Houston and everywhere you want to be.