The Venetian Causeway Water and Sewer Main Replacement project is underway. The contractor is working to replace the old water and sewer main with new pipes that will be installed underground.
Project Update
The contractor has completed the water main connections and will begin closing out Phase IV of this project.
Road repaving will commence on the north side of the causeway on Belle Isle and Rivo Alto. This work is expected to be completed by this week. The contractor will then proceed back to Phase II of this project, with traffic maintenance shifting to the south side of the Causeway.
Timeline
A full project closeout will take place by the end of the fall 2023. The project team anticipates that all traffic impacts will be removed by end of September 2023. Regular work hours will continue Monday through Friday from 7 a.m. to 7 p.m., with weekend work approved on a case-by-case basis.
Please know that this schedule may change due to weather or unforeseen circumstances.
Phase II – Traffic Changes
- The eastbound lane on Venetian Way between Island Ave will be closed.
- The eastbound lane on Venetian Way between East and West Rivo Alto will be closed.
- The westbound bike lanes and sidewalks will be open.
- The eastbound bike lanes and sidewalks will be closed.
|