View as Webpage

Venetian Causeway Water and Sewer Main Replacement

Project Advisory: Friday, August 11, 2023

The Venetian Causeway Water and Sewer Main Replacement project is underway. The contractor is working to replace the old water and sewer main with new pipes that will be installed underground.


Project Update

Road renovations on the north side of the causeway between Belle Isle and Rivo Alto are now complete, and the project will return to Phase II on Monday, August 14, 2023, for sewer main connections. Please be advised that this is the final phase of this project.


Due to the traffic plan changes, the left turn from Century Lane onto Venetian Way (eastbound) will be restricted. Traffic on Belle Isle will be redirected through Island Ave south. The city's Parking and Police Departments have committed additional resources to provide a seamless transition.


Timeline

A full project closeout will take place by the end of the fall 2023. The project team anticipates that all traffic impacts will be removed by end of September 2023. Regular work hours will continue Monday through Friday from 7 a.m. to 7 p.m., with weekend work approved on a case-by-case basis.


Please know that this schedule may change due to weather or unforeseen circumstances.


Phase II – Traffic Changes

  • The eastbound lane on Venetian Way between Island Ave will be closed.
  • The eastbound lane on Venetian Way between East and West Rivo Alto will be closed.
  • The westbound bike lanes and sidewalks will be open.
  • The eastbound bike lanes and sidewalks will be closed.

Belle Isle Traffic Changes - Phase II

Rivo Alto Traffic Changes - Phase II

What to Expect

  • Due to the partial closure of Venetian Way, residents will notice an increase in traffic through their neighborhood.
  • There may be construction noise due to drilling equipment.
  • Commuters to and from Miami Beach will face delays on the Venetian Causeway due to detours. 
  • There may be moderate noise impacts outside of normal working hours.
  • One lane of the Venetian Causeway will be open at all times.
  • Emergency vehicles will have access to the islands at all times.


Quick Access

For more information on this project, please see additional resources below:

Who to Contact

Gabriella Gonzalez, Neighborhood Affairs Coordinator at GabriellaGonzalez@miamibeachfl.gov