Venetian Islands Road Restoration Project

Project Advisory: Friday, December 1, 2023

Project Overview and Benefits

The City of Miami Beach is milling and resurfacing the residential streets on the Venetian Islands. This project will provide a uniform restoration process to the asphalt pavement on San Marino, Di Lido and Rivo Alto.

 

Construction activities include removing one inch of the existing asphalt pavement, repairing any damaged road base as necessary and placing two or more inches of new asphalt pavement to match the final elevation of the roadway. This process is expected to extend the life of the asphalt pavement by several years, and will finally bring the Venetian Islands Neighborhood Improvement project to completion.


What's Happening

Work will start on San Marino, followed by Di Lido and end on Rivo Alto. Access to driveways may be briefly restricted during certain operations. Please be aware that prior notice will be given.


We kindly ask that all vehicles, including commercial vehicles, refrain from parking on the road in order to complete this operation. Illegally parked vehicles will be towed at the owner's expense.


Timeline

Construction on the southern half of San Marino Island is already underway. Due to unforeseen circumstances, the contractor will continue to work until Tuesday, December 5, 2023. Work hours are weekdays from 8 a.m. to 4 p.m. In January 2024, work will resume to complete the northern half of San Marino, Di Lido and Rivo Alto Islands.


Please know that this schedule may change due to weather or unforeseen circumstances.


What to Expect

  • Moderate levels of construction noise and dust are expected during the day.
  • Construction equipment, machinery, flagmen and workers will be present.
  • Parking restrictions (“no parking” signs) will be posted within each work zone. All vehicles, including commercial vehicles, must refrain from parking on the road. Illegally parked vehicles will be towed at the owner's expense.
  • Please be cautious when driving around the construction zones and adhere to traffic signage.
  • Access to driveways may be impacted during certain operations.


Contact

For more information, please contact Gabriella Gonzalez, Neighborhood Affairs Coordinator at, GabriellaGonzalez@miamibeachfl.gov.

To learn more about the city’s innovative initiatives, visit www.MBRisingAbove.com.

To request this material in alternate format, sign language interpreter (five-day notice required), information on access for persons with disabilities, and/or any accommodation to review any document or participate in any city-sponsored proceedings, call 305.604.2489 and select 1 for English or 2 for Spanish, then option 6; TTY users may call via 711 (Florida Relay Service).