RELEASE: IMMEDIATE       

CONTACT: Paula Miller

HRBTinfo@VDOT.Virginia.gov

Friday, February 14, 2025

As part of the HRBT Expansion Project, construction crews will implement weekly lane closures, detours and traffic pacing on local roads, I-64 and the Hampton Roads Bridge-Tunnel. Travel restrictions include possible delays, reduced speeds and detours in some areas. Lane closures, detours and traffic pacing are subject to change based on weather conditions and other factors.


TRAFFIC ALERT: Starting February 14, 2025, 13th View/Bayville on-ramp to I-64 E in Norfolk will close temporarily. A detour is anticipated to be in place through April 2025. Read the full traffic alert HERE.


NOTE: Check the project webpage often for the latest updates to the weekly lane closures.

HAMPTON

Daytime Lane Closures and Detours

  • None


Overnight Lane Closures and Detours

Tuesday, February 18 through Thursday, February 20

  • Single lane closure on I-64 east/west from Hampton shoreline to Mallory Street from 9 p.m. to 5 a.m.


Wednesday, February, 19

  • Detour at Mallory Street on-ramp to I-64 east from 9 p.m. to 5 a.m.


Friday, February 21

  • Single lane closure on I-64 east/west at Mallory Street to HRBT from 9 p.m. to 7 a.m.
  • Detour at I-64 west Mallory Street on/off-ramp from 9 p.m. to 5 a.m.


Continuous Lane Closures and Detours

  • None
HAMPTON ROADS BRIDGE-TUNNEL

Daytime Lane Closures and Detours

  • None



Overnight Lane Closures and Detours

Tuesday, February 18 through Friday, February 21

  • Multiple stoppages on I-64 west at HRBT from 10 p.m. to 5 a.m.
  • Each stoppage may last up to 20 minutes.


Tuesday, February 18

  • Single lane closure on I-64 west at HRBT from 9 p.m. to 5 a.m.


Thursday, February 20

  • Single lane closure on I-64 east at HRBT from 9 p.m. to 5 a.m.


Friday, February 21

  • Single lane closure on I-64 east/west at HRBT from 9 p.m. to 7 a.m.


Continuous Lane Closures and Detours

  • None
NORFOLK

Daytime Lane Closures and Detours

Monday, February 17

  • Flagging at 4th View St from 9 a.m. to 3 p.m.
  • Flagging at 1st View St from 9 a.m. to 3 p.m.


Tuesday, February 18 through Friday, February 21

  • Flagging at Bayville St/13th View St from 9 a.m. to 3 p.m.
  • Flagging at Patrol Road from 9 a.m. to 3 p.m.
  • Flagging at 4th View St from 9 a.m. to 3 p.m.
  • Flagging at 1st View St from 9 a.m. to 3 p.m.
  • Flagging at West Bayview Blvd from 9 a.m. to 3 p.m.


Tuesday, February 18 and Wednesday, February 19

  • Detour at West Evans St from 6:30 a.m. to 8 p.m. CLICK HERE for detour map.


Wednesday, February 19 and Friday, February 21

  • Detour at W. Bay Avenue on-ramp to I-64 east from 9 a.m. to 1 p.m. CLICK HERE for detour map.


Thursday, February 20

  • Flagging at West Bay Ave from 9 a.m. to 3 p.m.


Overnight Lane Closures and Detours

Friday, February 14

  • Single lane closure I-64 east/west from Norfolk shoreline to Willoughby Bridge from 9 p.m. to 7 a.m.
  • Multiple stoppages I-64 east from Norfolk shoreline to Willoughby Bridge from 10 p.m. to 5 a.m.
  • Each stoppage may last up to 20 minutes.
  • Closure and detour of Bayville Street on-ramp to I-64 east CLICK HERE for the traffic alert.


Monday, February 17

  • Single lane closure on I-64 east/west at Norfolk shoreline to Willoughby Bridge from 9 p.m. to 5 a.m.
  • Multiple stoppages on I-64 west from Willoughby Bridge to Norfolk shoreline from 10 p.m. to 5 a.m.
  • Each stoppage may last up to 20 minutes.
  • Single lane closure on I-64 west from Patrol Road to West Evans St from 7 p.m. to 5 a.m.
  • Detour of Granby Street on-ramp to I-64 west from 9 p.m. to 5 a.m. CLICK HERE for detour map.


Tuesday, February 18

  • Single lane closure on I-64 west from Mason Creek Road to 4th View St from 7 p.m. to 5 a.m.


Tuesday, February 18 through Thursday, February 20

  • Single lane closure on I-64 east at Willoughby Bridge from 9 p.m. to 5 a.m.
  • Single lane closure on I-64 east from Mason Creek Road to Patrol Road from 7 p.m. to 5 a.m.
  • Single lane closure on I-64 east at 1st View St from 7 p.m. to 5 a.m.
  • Single lane closure on I-64 east at West Bay Ave from 7 p.m. to 5 a.m.


Wednesday, February 19 and Thursday, February 20

  • Single lane closure on I-64 west from 4th View St to Bayville St from 7 p.m. to 5 a.m.


Friday, February 21

  • Single lane closure on I-64 east at Willoughby Bridge from 9 p.m. to 7 a.m.
  • Single lane closure on I-64 east at 1st View St from 9 p.m. to 7 a.m.
  • Single lane closure on I-64 west from Mason Creek Road to 4th View St from 9 p.m. to 7 a.m.


Continuous Lane Closures and Detours

Friday, February 14 through Friday, February 21 (24 hours per day)

  • Closure and detour of Mason Creek Road at I-64 underpass CLICK HERE to read the traffic alert for the Mason Creek Road closure and detour map.
  • Closure and detour of Bayville Street on-ramp to I-64 east CLICK HERE for the traffic alert.

All construction schedules are pending weather or unforeseen circumstances. Please check the project website's Traffic Alerts page for updates.


Motorists should expect delays or take alternate routes. As always, motorists are encouraged to slow down, eliminate distractions and pay careful attention while driving through the construction zone. 


For additional travel alerts, motorists are encouraged to sign up for traffic alerts and project updates at HRBTexpansion.org, follow @HRBTExpansion on Twitter/X, visit 511virginia.org, call 511 or download the free Virginia 511 mobile app.

##

Facebook  Twitter  Linkedin  Youtube