Progress!!
The new contractor has been on-site all week, completing carpentry and other modifications in the Narthex addition. Drywall work will begin this Monday.
Thank you to all volunteers who cleaned the back of the church grounds of construction debris, which was hauled away on Friday. We will soon grade the back lot for proper drainage.
We continue to work on finding a manufacturer and installer for the large windows in the Narthex addition.
New flooring has been ordered for the existing Narthex as well as the new addition. Installation will take place as soon as possible.
New ceiling tiles will be installed in the existing Narthex and new addition by the contractor. Grids in the existing Narthex have been repainted.
The handicap lift has been received by the local distributor. It will be delivered and installed when the new contractor has the Narthex ready.
Modifications to the lower east entrance to the church will be undertaken once we have the Narthex addition completed.
The Vestry continues to thank the congregation for your patience and understanding as we complete this long-awaited project!
|