Main Street Water and Sewer Project
UPDATES
January 15th (MLK Holiday): sewer work to begin on Main Street at Morris Street intersection – Morris Street will be closed at this location.
After January 15th: sewer installation on Main Street to continue towards Chestnut Drive utilizing parking spaces on the east side of Main Street. Sewer installation continues on the east side of Main from Morris Street north to Maple Street through the end of February. Lane shifts will be expected during this construction and Fridays of each work will be reserved for clean up unless lost work days through the week.
February 5th: a new sewer crew mobilized to North Main for installation of 18-inch sewer and manholes from Chetola entrance to Hwy 321 light. Complete road closure of Main Street and a detour will be required each week Monday through Thursday. Friday-Sunday the road will be open. This portion of the project will last at least through the first of April 2024.
Mid-March 2024: water line installation will re-start from Ginny Stevens Lane and continue north on Main Street through downtown. The west side of Main Street parking and south bound lane will be utilized for water installation.
Entire water and sewer project completion date is September 10, 2024.
All dates listed are approximate and the timing of all construction activity is weather-dependent.
|