CONSTRUCTION UPDATE

Weeks of October 12 and October 19, 2026

Crews are actively working on several improvements along the corridor, including rebuilding sidewalks, driveways, and curbs, installing storm drains and utilities, and preparing for new streetlight and traffic signal foundations. These activities will continue over the next several weeks and may result in temporary impacts to driveways and pedestrian routes. Access to businesses and residences will be maintained.


Work will generally occur Monday through Friday during daytime hours (6:00 a.m. to 4:00 p.m.), with intermittent nighttime work (6:00 p.m. to 6:00 a.m.). Intermittent lane closures will take place along the project corridor, with at least one lane remaining open to traffic at all times. 

Crews installing utilities at Ontario Mills Bus Terminal as part of the West Valley Connector project.

All construction is dynamic and the schedule is subject to change. Visit the project Google Map for the most up-to-date scheduled closures and available detour routes.



Si prefiere recibir información de construcción en español, llame al (877) 55-SBCTA.

POMONA TRANSIT CENTER

Work at the Pomona Transit Center is anticipated during the week of October 12 to construct pads for new station equipment and systems. Construction activities will include concrete pad pouring and formwork, system installation, and increased noise in the area.



This work is not anticipated to impact the Pomona Transit Center’s schedule.

CENTER-RUNNING STATIONS

Construction is underway at the future West Valley Connector center-running stations along Holt Boulevard in Ontario. In the coming weeks, crews will continue work at the following locations:



  • Center-Running Station at Grove Avenue
  • Center-Running Station at Campus Avenue
  • Center-Running Station at San Antonio Avenue
  • Center-Running Station at Mountain Avenue


Work will include installation of station canopies and electrical equipment, construction and finishing of concrete bus pads and curbs, paving, and accessibility improvements. Crews will also continue landscaping and irrigation work at some station locations.


Pedestrian access will be maintained throughout construction. There may be construction equipment, increased truck activity, and noise near the work areas. Work activities may shift as construction progresses.

SIDE-RUNNING STATIONS

Outside lane closures are underway at the future station locations listed below. At least one lane will remain open to traffic at all times. Construction activities will include demolition of any current stations, roadway demolition, utility relocation, and construction of bus pads and new stations.


Pomona

  • EB Garey Avenue at Holt Boulevard


Ontario

  • EB and WB Vineyard Avenue at Holt Boulevard
  • Ontario Airport at Terminal 2 and Terminal 4
  • EB and WB Inland Empire Boulevard at Porsche Way


Rancho Cucamonga

  • Rancho Cucamonga Metrolink Station
  • EB and WB Milliken Avenue at Foothill Boulevard
  • EB and WB Rochester Avenue at Foothill Boulevard
  • Day Creek Boulevard at South Main Street (Victoria Gardens)


Pedestrian access will be maintained throughout construction, and no interruptions to bus operations are anticipated while this work is underway.

For information regarding Omnitrans bus service during construction, please visit Omnitrans.org.

WEST VALLEY BUSINESS CONNECTOR PROGRAM

This Week's Business Highlight:

This week’s business highlight is Action Mobile Homes. Action Mobile Homes has been helping customers buy and sell manufactured and mobile homes in Southern California for more than 30 years. The company offers a variety of new and resale manufactured and mobile homes, along with services to assist customers with buying, selling, and financing. Through its Ontario location and online resources, Action Mobile Homes provides customers with local expertise and support throughout the home-buying and selling process.


Contact:

(909) 986-2555

Website


Location:

1511 W. Holt Blvd., Suite F

Ontario, CA 91762

The West Valley Business Connector Program is designed to encourage the community to shop local during project construction. Participation is free for eligible businesses along the project route in the Cities of Ontario, Pomona, Montclair, and Rancho Cucamonga.


Participating businesses will be: 


  • Highlighted on @goSBCTA's social media platforms (Facebook and Instagram)
  • Shared in bi-weekly project construction alerts
  • Featured on the project webpage via Google Maps


To learn more and sign up, visit goSBCTA.com/WestValleyConnector.

ABOUT THE PROJECT

The West Valley Connector (WVC) project will be a 100% zero-emission Bus Rapid Transit (BRT) system, the first stage of the San Bernardino County zero-emission Bus Initiative and second BRT route in San Bernardino County.


Phase I of the project is 19 miles and will upgrade a portion of existing Route 61 which runs along Holt Boulevard, adding approximately 3.5 miles as center-running, dedicated bus-only lanes. There will be 21 stations in Phase I that will provide an improved transit connection to Ontario International Airport (ONT) and help build transit connectivity by linking ONT, two Metrolink lines (San Bernardino and Riverside) and multiple major activity centers along the route including Ontario Mills and Victoria Gardens. Headways will be 10 minutes in the peak commute period and 15 minutes off-peak, providing a high level of service to the community.

 