Capturing water is only part of the equation – the Valley also needs the infrastructure to move it. The Friant-Kern Canal is a critical example.
Land subsidence has reduced the capacity of a 33-mile stretch of the Friant-Kern Canal: at its most constrained point the canal carried about 1,600 cubic feet per second compared to its original design capacity of 4,000. Local, state, and federal partners are restoring it in phases, and a rebuilt 10-mile section is complete. On October 1, the Bureau of Reclamation and the Friant Water Authority broke ground near Porterville on five pump stations that will deliver canal water to Tea Pot Dome Water District and Saucelito Irrigation District, giving growers surface water in place of groundwater.
Each restored mile lets more wet-year water reach the eastside farms, communities, and recharge basins that rely on the canal.
|