Red.
Not amber-red. Not red-amber.
Red!
That’s the official verdict on the government’s Frontline Productivity Programme…
… the scheme intended to turn billions of pounds of NHS digital investment into measurable improvements in productivity.
The damming judgement comes from a Gateway Review.
Gateway Reviews are short, independent examinations of major government programmes, carried out at critical points in their development.
-
They test whether a programme has the leadership, governance, plans, resources and delivery machinery necessary to succeed.
-
They are not opinion polls, political commentary or press releases.
-
They are government looking under its own bonnet.
This one reports to the programme’s Senior Responsible Owner, the Department’s Accounting Officer and the Treasury
Its verdict could hardly be more serious. If this report were a novel, it would be about the Titanic.
Under the Gateway system, a Red rating means successful delivery to time, cost and quality appears unachievable.
Major problems exist and the programme may need to be re-baselined or have its overall viability reassessed.
The language of the report is restrained. The findings are not.
Treasury approved the programme’s business case in May.
By the time reviewers arrived in July…
-
there was no baselined, four-year delivery plan;
-
the programme board had met only once;
-
the intended senior Programme Director arrangements had not been established;
-
important delivery functions sat outside the control of the person accountable for delivery;
-
regional investment plans remained incomplete;
-
Year One funding had still not reached much of the frontline;
-
nobody had properly assessed whether regions and trusts had the people, capacity or digital maturity to deliver;
-
there was no integrated theory of change connecting the investments to the promised productivity;
-
there was a risk of benefits being duplicated or double-counted;
-
investment was being allocated largely through a fair share formula rather than according to need, readiness or achievable results.
This is not a programme running a little late. It is a programme that was approved and funded before anyone had finished designing how it would work.
The original plan was for regions to lead delivery, with the centre acting as funder, coordinator and commissioner.
Then came the reorganisation.
Regional capacity was cut.
Digital expertise was depleted.
ICBs and providers were thrown into uncertainty…
… at precisely the moment the programme needed strong regional delivery, the centre was dismantling it.
Meanwhile, ministers wanted tighter control over priorities such as cybersecurity and ambient voice technology.
What emerged was the mother-of-all-muddles.
Regions are nominally responsible but have fewer people.
The centre increasingly decides what must be bought.
Trusts have wildly different levels of readiness.
Nobody is clear who owns the benefits.
One of the report’s most revealing observations is that procurement is being handled locally while change support is being organised nationally.
That is exactly the wrong way round.
The NHS should use its scale to purchase technology nationally, but …
…changing clinical workflows, building confidence and making sure saved time becomes better care, can only happen locally.
Buying software is the easy bit. Changing how people work is the hard bit.
The most extraordinary sentence comes from the Senior Responsible Owner, Dermot Ryan. He agrees the Red rating is warranted because the operating model needs to be reset.
Then he says;
‘… the reset, falls outside of my powers to do.’
There it is. The luckless soul responsible does not have the authority to make the changes necessary to deliver.
-
Responsibility without authority.
-
Accountability without control.
The report then wrongly, in my view, directs its critical recommendations back to him.
This is not principally a failure of technology or the programme team, whose commitment the reviewers praise!
It is a failure of the machinery above them.
The government wants productivity while disrupting the organisations expected to deliver it.
It wants local leadership while pulling decisions towards the centre.
It wants multi-year transformation while operating use-it-or-lose-it annual budgets that encourage hurried spending.
It wants measurable benefits without a reliable way of connecting investment to results.
The NHS has approved a national programme to improve frontline productivity. The government’s own reviewers have concluded that the programme itself is not presently capable of delivering.
If that is true the Permanent Secretary’s responsibility is to ensure somebody very senior possess and can exercise, those powers…
… or tell ministers and the Treasury that the programme is not presently feasible.
This is about as serious as it gets. People's jobs, patient services, the digital future.
The frontline is not where the productivity problem begins…
… it begins in Whitehall.
|