Hello! Thank you for subscribing to our updates on the Winchester Street Reconstruction project. Please see a summary of recent and planned work below:
Recent work includes:
Completion of earthwork in support of concrete sidewalk installation
Forming and pouring of new concrete sidewalks south of Key Road and along Key Road
Forming for concrete sidewalks north of Key Road
Completion of retaining wall along Keene State College parking lot
Completion of new water services on Island Street and Pearl Street
Topsoil spreading and grass maintenance along Winchester Street
Temporary paving in support of removal of the Island Street Bridge
Upcoming work includes:
Temporary utility relocation in support of the Island Street Bridge reconstruction
Completion of concrete sidewalks and median islands south of Key Road
Connection of new water main to existing water main at Pearl Street
Completion of stormwater work for the Pearl Street / Island Street roundabout
Landscaping along Winchester Street and within the median islands
Street light installation along the median islands
Removal of concrete deck for the Island Street Bridge
The Island Street Bridge remains closed to vehicles. Detour maps are available on the project website to help guide road users. The bridge subcontractor is currently behind schedule; the bridge has remained open until now for pedestrian use. Once we receive a fully updated schedule, we will provide another community update.