Winchester Street Reconstruction Project Update

June 1, 2023

Hello! Thank you for subscribing to our updates on the Winchester Street Reconstruction Project. Thank you for your patience; we understand we have not provided an update for several weeks. Please drive slowly and watch for equipment and laborers in the work zone.


Recent work includes:


  • Completion of water main installation south of the Island Street Bridge
  • Completion of sewer work south of the Island Street Bridge
  • Storm water installation for the Pearl Street / Island Street roundabout
  • Installation of granite curbing for the Key Road roundabout
  • Completion of concrete truck apron at the Key Road roundabout
  • Earthwork in support of future sidewalk reconstruction
  • Excavation for the new retaining wall along the Keene State College parking lot
  • Installation of light pole bases
  • Asphalt removal on the Island Street Bridge
  • Private overhead utilities have completed relocation in support of the project


Upcoming work includes:


  • Connection of new water main to existing water main at Pearl Street
  • Installation of water services near the Island Street Bridge
  • Completion of storm water work for the Pearl Street / Island Street roundabout
  • Completion of earthwork in support of concrete sidewalk installation
  • Forming for concrete sidewalks
Project Photos

The Island Street Bridge remains closed to vehicles. Detour maps are available on the project website to help guide road users. The bridge subcontractor is currently behind schedule; the bridge has remained open until now for pedestrian use. Once we receive a fully updated schedule, we will provide another community update.


As always, please check out the project website or the Keene Public Works Facebook page for updates as things progress. Thank you!


If you have any questions regarding this post please call our office at 603-352-6550.


City of Keene, Public Works Department