Main Street Revitalization

Construction Update

May 15, 2026

Traffic and Parking Impacts:

Main Street between Spring Street and Tigan Street:

Next week, motorists can expect parking restrictions, lane reductions, and traffic shifts on Main Street between Spring Street and Tigan Street. Two-way traffic will be maintained, with the potential for alternating one-way traffic. Flaggers will be stationed at multiple locations to direct traffic at side street intersections. “No Parking” signs will be posted where on-street parking is restricted.


From Monday, May 18, through Wednesday, May 20, traffic on Main Street near the Winooski Fire Department (Maple Street/Union Street area) will experience temporary traffic stoppages of up to 10 minutes between 7 AM and 7 PM while crews install traffic signal mast arm poles.


On Thursday, May 21, and Friday, May 22, similar temporary holds of up to 10 minutes (7 AM to 7 PM) will occur at the Main Street and Spring Street intersection for traffic signal mast arm pole installation. Lane reductions and traffic shifts will also be in effect on East and West Spring Street, with two-way traffic maintained.


The Main Street southbound approach to the Tigan Street intersection has been reduced from two lanes to one lane to improve driver safety. This lane reduction will remain in place 24/7 until final striping and pavement markings are installed later this construction season.


Pedestrians should follow all posted sidewalk closure signs and detour routes as sidewalk excavation and installation take place on Main Street between Lafountain Street and Tigan Street throughout the week, and on Normand Street on Thursday and Friday. Pedestrian access will be maintained along Main Street and to the Winooski School District.

 

Adjacent Project Impact: Weaver Street Utility Work

From May 21–22 and May 28–29, on-street parking will be temporarily restricted on the west side of Weaver Street near 168 Weaver Street, just south of the West Spring Street intersection, to accommodate independent utility work. The restricted area will be clearly marked with cones and signage.

Property Impacts:

Monday and Tuesday, driveway access interruptions of up to 48 hours are expected along the east side of Main Street just north of Lafountain Street (weather permitting) as crews complete sidewalk excavation and installation.


On Wednesday, sidewalk work will shift to the west side of Main Street, beginning near Bellevue Street and progressing north. Driveway impacts are not anticipated for this work next week. In the following weeks, crews will install driveway aprons along this segment, which will require temporary driveway closures. These closures are expected to last 2–3 days, depending on whether the apron is asphalt or concrete. Additional notice will be provided in advance to help property owners plan accordingly.


The contractor will notify impacted property owners, residents, and/or businesses ahead of time by knocking on doors and leaving notices. The notices have QR codes that link to videos with information in 14 additional languages.


العربية | မြန်မာစာ | دری | English | Français | Kirundi | Maay Maay 

官话 | नेपाली | پښتو | Soomaali | Español | Kiswahili | українська | Tiếng Việt

Construction Activities:

Crews will work on weekdays between 7 AM and 7 PM, with an early stop at 3 PM on Friday, May 22, and no work on Monday, May 25, in observance of Memorial Day.


Crews will adjust frames and grates on Main Street between Stevens Street and Tigan Street, and finish installing streetlight wiring between Bellevue Street and Tigan Street on Monday and Tuesday.


Crews will complete sidewalk excavation and installation on the east side of Main Street near 259 Main Street (just north of Lafountain Street) on Monday and Tuesday, before shifting to the west side on Wednesday, starting near Bellevue Street and progressing north. On Thursday and Friday, crews will excavate sidewalk on Normand Street.


Permeable paver installation will continue on the east side of Main Street, from just north of Lafountain Street to Tigan Street from Monday through Wednesday. On Tuesday and Wednesday, crews will prepare for paver installation on the west side between Bellevue Street and Tigan Street, before beginning installation on Thursday.


Near the Winooski Fire Department, crews will install traffic signal mast arms and wiring throughout the week. At the Main Street and Spring Street intersection, crews will install traffic signal mast arms and wiring on Thursday and Friday.


Please note, the schedule is subject to change due to weather and other variables. 

Project Overview: The City of Winooski is upgrading Main Street (U.S. Route 2/7). The Winooski Main Street Revitalization project will reconfigure the road layout to accommodate all users. The project will:


  • add crosswalks and bike lanes, and expand sidewalks,
  • upgrade traffic signals, and
  • enhance the street's appearance with lighting and landscaping.


The project will improve utilities by:


  • installing new stormwater systems,
  • upgrading existing sewer and water, and
  • moving existing power and communication lines underground.


Construction started in the spring of 2024 and is anticipated to continue over three construction seasons until the summer of 2026.

Project Location: Main Street (U.S. Route 2/7) in Winooski from the New England Central Railroad bridge near the intersection with Maple Street, extending approximately 4,000 feet to the north to the Winooski-Colchester town line near the Winooski School District.
Projected Completion: Summer 2026
Contact Information:
Please contact us if you have any questions, comments, or concerns regarding the project.

Project Hotline: 802-595-4399
Project Area:

Nearby Construction Project Highlights:

VTrans Exit 16 DDI Project

  • Project Area: I-89 Exit 16, U.S. 2/7 between Tigan Street and Sunderland Woods Road
  • Next week: Sunday through Thursday, during nighttime hours, crews will conduct milling, box cutting, and temporary paving along U.S. 2/7 between South Park Drive and Mountain View Drive and the I-89 southbound off-ramp. Monday through Friday, during daytime hours, crews will maintain roadway surfaces and conduct traffic signal work along U.S. 2/7 between South Park Drive and Mountain View Drive, and near Hercules Drive, working north.
  • Traffic Impacts:
  • Sunday – Friday, 7 PM – 6 AM | Lane closures along U.S. 2/7 between South Park Drive and Mountain View Drive, with traffic shifts.
  • Monday – Tuesday, 7 PM – 6 AM | South Park Drive reduced to a single lane at U.S. 2/7. Access will be maintained.
  • Thursday, 7 PM – 6 AM | I-89 southbound off-ramp fully closed with traffic detoured to exit the interstate at Exit 17 onto U.S. 2 to U.S. 2/7.
  • Monday – Friday, 9 AM – 3 PM | Lane closures along U.S. 2/7 between South Park Drive and Mountain View Drive, and near Hercules Drive moving north.
  • Monday and Tuesday, 9 AM – 3 PM | Highgate Center reduced to a single lane at U.S. 2/7. Access will be maintained.
  • Gravel, uneven conditions on U.S. 2/7 from Sunday night through Friday. Significant delays are expected during work hours. 
  • Project website
  • Construction: Summer 2025 – Summer 2027

VTrans Colchester Exit 17 Project

  • Project Area: I-89 Exit 17, U.S. 7 between the Shell Gas Station and Wiley Road, U.S. 2 between Chimney Corner and Jasper Mine Road
  • Project Update: Crews will be off-site until June 2026 for overhead sign installation.
  • Project Website
  • Construction: Spring 2024 – Summer 2026