DATE: Thursday, 10/20/22
TRAFFIC IMPACT:
Little to no traffic impacts anticipated throughout the week of 10/23/22.
CONSTRUCTION ACTIVITIES:
Painting of stop bars, crosswalks and roadway symbols has been completed.
Sign installation remains and is currently scheduled for next week. This work will be completed during daytime hours and will not have a large impact on traffic.
Signal work has been completed. Installation of flashing pedestrian beacons at various locations throughout the project still remains and will likely take place in mid-November. This work will be performed during daytime work hours and will not have a large impact on traffic.
Project-wide clean-up will continue along the entire project limits and will include topsoil, seeding and mulching along areas that have been disturbed throughout the construction process. This will occur intermittently over the course of the next several weeks.
On the abutting Burlington project, painting operations will finish up at the intersection of Colchester Avenue and Riverside Avenue and continue along Riverside Ave. Please anticipate that work in this area will cause delays.
|