DATE: Friday, 9/30/22
TRAFFIC IMPACT:
One-way alternating traffic patterns will be in effect in areas of active construction throughout the week of 10/2/22. Please anticipate minor delays.
CONSTRUCTION ACTIVITIES:
Painting of stop bars and cross walks is scheduled for next week. Painting of symbols (arrows, etc.) will occur later in the week or the following week.
Please expect alternating traffic and delays in the vicinity of painting operations. Adverse weather and/or surface conditions can alter or delay the painting schedule.
Project-wide clean-up will continue during the late-afternoon hours along the entire project limits. This will occur intermittently over the course of the next several weeks.
Work on this contract will be performed at night. All nighttime work hours are 7:00 p.m.-6:00 a.m. Sunday through Thursday night. It should be noted, however, that work may be performed at times on Friday nights.
|