Construction Update
U.S. Route 7 and East Allen St.

DATE: Friday, 11/18/22


TRAFFIC IMPACT:


No anticipated traffic impacts.



CONSTRUCTION ACTIVITIES:


Work on this project has largely been completed for the season. The installation of flashing pedestrian beacons at various locations throughout the project remains. This work will have minimal impact on traffic when it occurs.


The contractor will return in the spring to complete any remaining miscellaneous project-related items.


This will be the last regular weekly update for this season. Intermittent alerts will be sent if required.

LOCATION:  This project begins on US-7/US-2 (Colchester Ave) at the Winooski/Burlington Town Line and continues northerly along US-7/US-2 (Main Street) to the Winooski/Paving Town Line. The project also begins at the Winooski Circulator on VT-15 (East Allen Street) and extends easterly along VT-15 (East Allen Street) to the Winooski/Colchester Town Line at the Class 1 Town Highway limit.

PROJECTED COMPLETION: November 2022
Contact Information:
Name - Natalie Boyle
Phone - (802) 855-3893