Construction Update
U.S. Route 7 and East Allen St.
DATE: Friday, 6/17/22

TRAFFIC IMPACT:

One-way alternating traffic will be required in the vicinity of nighttime operations.

Please use caution and reduce speed when driving through the construction zone. Structures will remain raised until the wearing course of asphalt has been paved.

CONSTRUCTION ACTIVITIES:

Rehabilitation of drainage structures will continue Sunday night, 6/19 and continue for the entire week. Work will begin at the intersection near the interstate and progress toward the circulator. This work will be ongoing for several weeks.
This operation is of a more "static" nature and residents should expect sustained noise and lighting at the location of each structure.

Work will begin on the traffic island in the same vicinity (near Dion Street) and will be ongoing for several weeks.

LOOK AHEAD:
Removal of the concrete slabs on Route 7/West Allen Street (near Four Quarters) is scheduled to begin the week of 6/26.
Work on this contract will be performed at night. Typical nighttime work hours are 7:00 p.m.-6:00 a.m. Sunday through Thursday night. It should be noted, however, that work may be performed at times on Friday nights.
Paving of shim has been completed.
LOCATION:  This project begins on US-7/US-2 (Colchester Ave) at the Winooski/Burlington Town Line and continues northerly along US-7/US-2 (Main Street) to the Winooski/Colchester Town Line. The project also begins at the Winooski Circulator on VT-15 (East Allen Street) and extends easterly along VT-15 (East Allen Street) to the Winooski/Colchester Town Line at the Class 1 Town Highway limit.

PROJECTED COMPLETION: November 2022
Contact Information: