Your go-to source for Association and transportation industry news, notes, and need-to-knows | | WTBA sincerely thanks its 2026 Weekly Update sponsors: Brooks Tractor, County Materials Corporation, Fabick Cat, and Roland Machinery Company. Please click on the logos to reach their respective websites. | | |
IN THIS WEEK'S EDITION
NEWS & NOTES
- Hoping to avoid two-year delay and $22 million extra cost, WisDOT aims to shift I-94 East-West let schedule
- Design-Build conflict of interest information now available
- Blatnik Bridge public hearing with Ames-Kraemer set for next week in Superior
- WTBA files court documents for clarity on claims process
EVENTS & REMINDERS
- A delight in the desert: Book your Annual Convention room NOW!
MEMBER SPOTLIGHT
- Lawmakers check in on member progress on Germantown roundabout project
- LWM magazine features WTBA safety efforts
INDUSTRY INSIGHTS
- 137 firms recertified, but DBE goals not likely to return before 2027
- REMINDER: Fill out FHWA Form 1391 before August 14
| | More funding, shifted let schedule necessary to avoid two-year delay on I-94 East-West | | Crews work on concrete wall coping and facing near Wood National Cemetery along the I-94 East-West project August 5, 2026. (Photo courtesy Justin Thomas / Zignego Group) | |
Significant utility relocation issues could delay the massive I-94 East-West expansion in Milwaukee by two years and cost tens of millions more.
WisDOT hopes to avoid that by starting construction on other elements of the $1.8 billion freeway reconstruction sooner.
Secretary Kristina Boardman briefly detailed the issue in her latest report to the Transportation Projects Commission this week.
Instead of waiting on utilities to take care of their responsibilities, WisDOT could reconfigure let packages planned for later years–such as converting the Stadium Interchange into a diverging diamond–to earlier dates. Doing so would save the state about $22 million in delay costs but would also require lawmakers to commit more transportation funding in the next two state budgets.
| | |
That will only add pressure on the Transportation Fund as a new governor and legislature begin crafting the next state budget in 2027.
Recent state transportation budgets have largely avoided tough funding decisions by using General Fund surplus revenues to meet growing infrastructure needs.
Work began on expanding 3 ½ miles of the busy freeway running in front of American Family Field in 2025. The project website currently shows construction finishing in 2033, but the delays would extend that into 2035.
| | | |
WTBA members including Zignego Group, Zenith Tech, Inc., and Edgerton Contractors are all working on the project.
Zignego Senior Project Manager Justin Thomas tells WTBA crews finished the delicate job of carefully pressing in sheet piling along the cemetery border in July. This week, they're placing storm sewer piping to tie into the mainline system (seen above).
DESIGN-BUILD SHOULD SAVE MONEY ON I-39/90/94
Boardman’s report to the TPC also highlights the advantages of the WTBA-backed Design-Build legislation, which Gov. Tony Evers signed into law earlier this year.
WisDOT plans to use Design-Build to replace the Mirror Lake Bridges as part of the 67-mile reconstruction of I-39/90/94 between Madison and Wisconsin Dells.
Boardman says Design-Build will save time and money on the bridge project, reducing the overall estimated cost of the full reconstruction by about $300 million. Updated estimates place the overall cost at $4.6 billion, based on expected inflation by the early 2040s.
The Transportation Projects Commission meets each December. It recommends projects for funding in the state budget in even-numbered years and recommends future projects for study in odd-numbered years.
Studies to expand I-94 in Waukesha County and reconstruct US-53 in Eau Claire—both recommended by the TPC in December 2025--are getting under way, Boardman says.
| | WisDOT releases conflict of interest information ahead of next Design-Build project | | |
Contractors and consultants now have guidance on what qualifies as a conflict of interest in future Design-Build projects.
WisDOT recently published a document detailing what would make a firm ineligible to participate. You can review it HERE.
Some disqualifiers include being the General Engineering Consultant on the project, preparing the Request for Proposal language, previously working with key stakeholders on the project, and other factors.
WisDOT expects firms to self-report potential conflicts of interest and will generally not provide contractors with a list of known conflicts ahead of them submitting statements of qualification.
However, the department is doing all it can to limit conflicts, Deputy Administrator Michael Hoelker told the WTBA Board of Directors on Tuesday.
| | |
The department plans to use Design-Build to replace the aging Mirror Lake Bridges along I-39/90 near Wisconsin Dells. Hoelker says a request for qualifications (RFQ) will likely go out sometime this fall.
The state can use up to $300 million every two years on Design-Build projects thanks to a new law which WTBA helped pass in 2025.
| | Blatnik Bridge public meeting scheduled for August 12 | | |
The public will get its first look at the winning design plan for the massive Blatnik Bridge replacement project next week.
WisDOT and lead agency MnDOT will hold a public meeting Wednesday, Aug. 12 from 5-7 p.m. at the Superior High School Performing Arts Center.
| | | |
The prime contractor–a joint venture between Ames and Kraemer North America–will share information on its new bridge design, the overall project timeline, traffic impacts and more.
MnDOT awarded Ames-Kraemer the Design-Build project over Lunda Construction on June 23. Ames-Kraemer’s bid was $930 million, well below the estimated $1.8 billion project cost.
MnDOT’s Design-Build process meant calculating an “adjusted score,” which divides a bidder’s overall price with its technical proposal score. The lower the adjusted score, the better. Lunda actually posted a better technical proposal score (93.20) than Ames/Kraemer (91.38) but also came in with a much higher proposal price, which inflated Lunda’s overall adjusted score.
Those unable to attend the in-person meeting next week can review the open house materials after the event on the Blatnik Bridge project website.
Phased construction, including a full closure of the existing bridge, is scheduled to begin in early 2027, with the full project scheduled for completion in 2032.
| | WTBA court filing seeks clarity on claims | | | | |
WTBA has filed a "friend of the court" brief in an appeals case, questioning whether WisDOT can reject contractor claims outright by asserting the Wisconsin Constitution doesn’t allow them.
Last year, a Milwaukee Circuit Court decision in Walsh v. WisDOT embraced the state’s argument that a claim made by Walsh Construction was not allowable because the state agencies were insulated from such claims by the Wisconsin Constitution.
| | |
The breadth of this interpretation and the precedent it could set raised concerns with WTBA and other groups including Wisconsin Manufacturers and Commerce (WMC), whose members also do work with the State of Wisconsin.
As a result, both WTBA and WMC have filed amicus briefs in Walsh’s appeal of the lower court ruling and seek greater clarity on when claims against the state may be allowed.
WTBA contends that–absent a clear and fair claims process–contractors have few options other than broadly building any potential risks into their bids. WTBA argues that could have negative ramifications for the taxpayers by inflating the cost of state projects.
You can read the WTBA brief HERE.
The appeals court’s next step is to rule on whether it will hear oral arguments in the case. There is no deadline for that decision but WTBA will keep members updated when it happens.
| | Book your room TODAY for upcoming Annual Convention in Scottsdale | | |
If you already know you’ll be joining us for the 2027 WTBA Annual Convention in Arizona, why wait to book your accommodations?
The room block for the Grand Hyatt Scottsdale Resort is open now.
The convention runs Sunday, Feb. 21 through Thursday, Feb. 25, 2027.
WTBA attendees can book their stay at the discounted group rate of $489/night, which includes the daily resort fee, by clicking the link on the event details page HERE.
Please note: Suite upgrades are available, but extremely limited. If you’re interested in asking about suite availability, please call the reservations desk at 480-444-1234.
The Grand Hyatt Scottsdale is a luxury resort surrounded by the Sonoran Desert and scenic mountains, with multiple on-site restaurants, fantastic pools, access to world-class golf and more. It went through a $115 million renovation in 2024.
Details on daily convention events, general sessions, activities, and dining–including registration for the conference itself–are coming this fall.
| | Quick and Quiet: Musson Bros. shows lawmakers advantages to full road closure during WTBA tour in Germantown | | |
The intersection of Highway 145 and County G in Washington County was about as quiet as a construction zone can be Thursday afternoon.
A mini excavator sat still while a few workers took a break and the only cars moving by were in and out of the garage of a nearby auto repair shop.
It’s the kind of work zone Bob Draths wishes he had all the time.
“We’re lucky here,” Draths told WTBA as he walked around the project.
| | |
Lucky because signs and barricades fully close the well-traveled crossroads near Germantown while Draths and his prime contractor Musson Brothers, Inc. crews and subs build a roundabout.
Thursday was especially quiet because concrete was curing and Draths was waiting on final grading, paving, and electricians to come in, but the project has been a flurry of activity since construction started June 10.
| | | |
“Sometimes it is a big inconvenience to the traveling public to shut a road down like this, but it allows us to get it done quicker, safer and for less cost,” Draths explained. “You can kind of put every dollar into the finished project right out of the gate.”
What could take six months or more to finish if the state required traffic flow, temporary roadway, and multiple stages instead can be finished in 2 ½, before the end of August.
That was welcome news to the three state lawmakers joining Draths and WTBA Director of Government Affairs Elise Nelson on the quick tour.
| |
State Reps. Dan Knodl and Paul Melotik and State Sen. Jodi Habush Sinykin took advantage of the relatively peaceful site to bounce questions off Draths and Nelson about work zone safety, transportation funding, project design, and industry workforce.
“I’m so glad you invited us because this really is relationship building,” Habush Sinykin said. “This is so much better than sitting, talking in an office. It’s great to see this investment.”
The $1.8 million investment is far from the busiest or grandest project lawmakers can see during this summer’s WTBA legislative tours across Wisconsin, but it’s an important one nonetheless – vastly improving safety at a place that once had poor sight lines and numerous crashes.
For that, Draths is thankful and proud to explain loud and clear: these small projects add up to make a big difference.
“There’s obviously way more of these that go on than the big ones. People can stop and appreciate this, the people who drive through this drive through it all the time,” Draths said. “It’s really good to get these built for the local communities.”
| | League of Wisconsin Municipalities magazine features WTBA safety efforts | | | | |
Leaders in hundreds of communities across Wisconsin can now better understand the important work WTBA has done to improve work zone safety and the role those communities play in the ongoing process.
The latest edition of the League of Wisconsin Municipalities’ monthly magazine features a two-page spread called “Changing Lanes: Rethinking Work Zone Safety in Wisconsin.”
| | |
The article covers WTBA’s work to help craft a robust schedule of events during Work Zone Awareness Week, the flagger pilot safety study, Work Zone Safe Wisconsin online education, and tips for how municipalities can improve safety in work zones based on access and permitting.
Click HERE to read the article, which is located on pages 19 and 20.
| | WisDOT recertifies 137 DBE firms, but new goals not likely before 2027 | | |
Disadvantaged Business Enterprise (DBE) program goals will likely not return before 2027.
WisDOT is currently reviewing Federal Highway Administration comments on its DBE program plan, department leaders told the WTBA Board of Directors this week.
The state approved 137 firms as part of its required recertification process this year. The original list had nearly 1,300 firms, but only about 200 of those actually did work on state projects.
| | | |
The USDOT required all states to recertify DBE firms without using the assumption of race or gender-based disadvantages following a rule last fall. WisDOT removed its DBE goals from all projects starting with the October 2025 let.
DTSD Administrator Rebecca Burkel says WisDOT is currently drafting potential triennial goals and will work with stakeholders, hold a public comment period, and get federal approval before setting new project goals, but that will likely not happen until next year.
| | REMINDER: Contractors required to fill out federal form by August 14 | | |
Contractors currently working on most federally funded projects in Wisconsin need to submit a required form by next week.
WisDOT says all primes and subcontractors working active state-let highway projects with federal funding at a contract level of at least $10,000 must fill out FHWA Form 1391 by Friday, August 14, 2026. Note: this does not include airport projects.
You can find the form, how to fill it out, who to submit it to, and all other important information HERE.
Form 1391 tracks workforce demographics such as race, apprenticeships and on-the-job training. The form is an Excel document that auto-populates as contractors enter their information. Companies then email the completed document for each project to the USDOT.
Unsure if your project qualifies? WisDOT's webpage has step-by-step guides on how to search projects within both CRCS and AWP CRL.
| | CONNECT WITH US ON SOCIAL | | | | |