CONSTRUCTION ADVISORY
February 21, 2019
Expanded Hours for Narrowed Traffic Flow Inside Terminal B/C Pedestrian Bridges
Walkways will be narrowed 24/7; Access between terminal and
Metro station will be maintained
Summary of Impacts
  • Beginning on or about February 21, pedestrians will navigate narrowed paths between Terminal B/C and the Metro station 24 hours a day.
Details
  • Beginning on or about February 21, construction crews will build a protective walkway in the pedestrian bridges connecting Terminal B/C and the Metro station.
  • The center walkway within the pedestrian bridges will be closed.
  • Moving walkways on the bridges will be turned off, and pedestrians will be routed through narrower paths to enter and exit the terminal.
  • To keep people moving within the narrowed space, signs will direct traffic flow.
Project Benefits

Timing
  • Constructing the protective walkway will take several weeks. This walkway will then serve as the connection point between Terminal B/C and the Metro station.
  • The protective walkway will remain in use until heavy construction of two new security checkpoints is complete, estimated for 2021.