The Stormwater Beach Outfall Project continues to advance ahead of schedule and has now entered its final roadway, drainage, and watermain phase. Utility work between 4th Ave N and 1st Ave N is substantially complete, and construction has moved south toward 2nd Ave S, where major roadway and utility improvements remain on track for completion by the end of the year.
To date, crews have installed 6,600 of the project’s 9,600 linear feet of storm drainage infrastructure (69%), 4,300 of 6,100 linear feet of watermain (70%), and 73 of 113 inlet and manhole structures (65%). The project’s 3,200 linear feet of 36-inch HDPE offshore outfall pipe is fully installed (100%).
Offshore work reached another major milestone with the successful installation and testing of the two 36-inch outfall pipes before sea turtle nesting season. Diffuser installation is approximately 90 percent complete, with crews finishing work at the North Pump Station diffuser before moving south. This approach aligns with pump station construction and supports the planned startup and testing of the South Pump Station between September and October of this year. The North Pump Station is approximately 75 percent complete, with remaining structural, mechanical, and electrical work continuing into early 2027.
Restoration efforts and other project elements are progressing as well. Landscaping improvements at Alligator Lake have restored the park’s original charm, and installation of the pinch valve that will connect the lake to the South Pump Station is expected in the coming weeks.
Overall, the project remains ahead of its baseline schedule, with an estimated completion date of May 2027, or potentially sooner.
|