Long Bridge Project

November 2026 Monthly Construction Update

Thank you for signing up for the Long Bridge Project updates. This monthly construction update is intended to keep you informed on upcoming construction activities, travel impacts, and progress.  

Highlights This Month

The Washington Trestle Construction



Before crews can build a new rail bridge across the Washington Channel, they first need a way to reach it. The Washington Channel trestle is a temporary work bridge built exclusively for construction crews. The existing rail bridge and 14th Street leave little room to work from the west side, so crews need to build from the east. The trestle makes that possible by providing access across the channel, connecting the Washington Marina parking lot to Ohio Drive in East Potomac Park. Watch our latest video to see how the trestle was built!


Check out our YouTube channel for more construction updates.

Holiday Hours



This holiday season, VPRA is grateful for your patience as we continue construction on this important project! Our crews will not be working over the Thanksgiving holiday, including Thursday, November 26 and Friday, November 27.

Current Travel Impacts


Visit the Construction Disruptions Map to view all travel impacts. All schedules detailed below are subject to change and weather permitting.


Washington, DC


  • D Street SW: Construction activities near L'Enfant Plaza will continue through November 20, 2026. Temporary daytime lane closures and pedestrian detours will remain in place to support ongoing work.
  • Northbound 14th Street SW: Temporary right lane closures near Maine Avenue SW will continue through December 31, 2026, Monday through Friday, from 9:30 a.m. to 3:30 p.m., to accommodate construction material deliveries. 
  • I-395  
  • Southbound Ramp to Ohio Drive SW: Continuation of temporary traffic stops on the exit ramp from I-395 to Ohio Drive SW through December 2026, Monday through Saturday from 7:00 a.m. to 6:00 p.m. 
  • Southbound: Continuation of intermittent temporary daytime lane closures on southbound I-395, from East Potomac Park (Exit 2) in DC to the George Washington Memorial Parkway (Exit 10) in Virginia through the end of 2026.  
  • Northbound: Temporary right lane closures on northbound I-395, from the Potomac River to Exit 2 (Potomac Park), will continue through November 14, 2026. Work will occur Monday through Saturday, from 9:30 a.m. to 3:30 p.m. Crews will install temporary concrete barriers and receive deliveries. Exit 2 will remain open. 
  • Northbound Express Lanes Ramp: Temporary overnight closures of the northbound I-395 Express Lanes ramp connecting to the northbound general-purpose lanes near East Potomac Park will continue through November 14, 2026. Closures occur Monday through Friday, from 10:00 p.m. to 6:00 a.m., and Saturdays, from 9:00 p.m. to 6:00 a.m. Motorists will be directed to follow the posted detour. 
  • Ohio Drive SW: Continuation of intermittent daytime single-lane closures on Ohio Drive SW, between the Metro Yellow Line Bridge and the existing railroad bridge. 
  • Eastbound Ohio Drive SW: Eastbound Ohio Drive SW traffic will be temporarily detoured beneath the existing railroad bridge near the Washington Channel. The detour is anticipated to continue through the end of November 2026, Monday through Saturday, from 7:00 a.m. to 5:00 p.m. Westbound traffic will remain open toward I-395 and the Jefferson Memorial.
    

Virginia


  • George Washington Memorial Parkway: Intermittent daytime single right lane closures on southbound George Washington Memorial Parkway are anticipated to continue through January 2027.

November Construction Look Ahead

Exit 2 Ramp from Southbound I-395

Washington, DC


  • With the piles driven and the concrete pile cap complete, crews will continue building the D.C. rail abutment for the new Potomac River bridge along Ohio Drive SW through November. Upcoming activities include additional concrete pours for the abutment wing walls, advancing construction of the above-ground structure that will support the future rail bridge.  
  • Construction will continue along the I-395 corridor, including work behind existing traffic barriers, installation of foundation piles, and preparations for drilled shaft construction. Additional drilled shaft activities are anticipated to begin toward the end of November. 
  • Crews will continue retaining wall construction and related activities along Maine Avenue SW in preparation for the upcoming long-term traffic configuration scheduled to begin as early as mid-December 2026.

Potomac River, looking towards DC

Virginia & the Potomac River

  • Crane mobilization and movement will continue within the Virginia-side construction site to support upcoming foundation work. Crews will continue to prepare the Virginia rail abutment for the new Potomac River rail bridge and pier areas for subsequent construction activities. 


  • The first of the massive foundation piles for the new rail bridge will be driven this month. The large pipe piles are being floated upriver about 65 miles from an off-site facility where they are stored and prepared for the site. This work will mark the next phase of foundation construction within the Potomac River.  

Pipe pile barge delivery

  • Marine traffic control measures will remain in place throughout construction. Boaters should follow all posted navigational aids and signage and use caution when navigating the area. 

Construction Progress

  • Crews advanced preparations for in-water foundation construction, including the initial delivery of massive pipe piles by barge to the work site. Transporting these structures by water means avoiding more than 100 delivery trucks on local roads, helping reduce roadway congestion and construction-related traffic.

Thank You for Staying Informed!

Have any questions or comments? Share them with our project team. Make sure to also follow us on social media for updates throughout the month.

 

Email: info@longbridgeproject.com 

 

Phone: (202) 769-1808 


Facebook    LinkedIn    YouTube    Instagram

Project Description

The Virginia Passenger Rail Authority’s Long Bridge Project is a 1.8-mile rail improvement that will relieve one of the biggest rail bottlenecks on the East Coast. The project will improve reliability and expand capacity for both passenger and freight trains traveling between Virginia and Washington, DC. 

 

The project will create a continuous four-track corridor between the Long Bridge Aquatic Center in Arlington and L’Enfant Plaza in DC. It includes five new rail bridges and two new pedestrian/ bicycle bridges. A new two-track rail bridge will be built over the Potomac River next to the existing two-track Long Bridge, along with a new bike and pedestrian bridge connecting Long Bridge Park and the Mount Vernon Trail in Arlington to East Potomac Park in DC.


The Long Bridge Project is one of the Virginia Passenger Rail Authority’s many rail projects across the Commonwealth. Learn more at: www.vapassengerrailauthority.org.

 

Learn More & Stay Connected

Know someone who´d like to receive email updates about traffic impacts, public events, and project milestones? Sign up for updates here.

Please do not respond to this email. For questions, contact info@longbridgeproject.com.