I have a comically large Gantt chart in my office tracking our building project’s progress (it lives next to a sign that says “Hello, I’m weird about pens”, lest you worry that this project has fully changed me) and it gives me no small sense of joy to see that things are progressing as they should. And this means that I have some updates for you!



Read on for details about:

  • RTU-6--and the service disruption we’ll have when this unit is installed
  • Where we are with the retaining wall


A recap: RTU-6 is our incoming rooftop (RT) unit (the sixth HVAC unit at the Library) which will replace the unit that failed last summer. The goal? A cool mezzanine and second floor when it gets hot outside!


Our engineers and contractors have spent the past few months doing the preparatory work for the installation of this sci-fi sounding piece of machinery, which is why the mezzanine has been closed. There’s been welding, there’s been duct work, the roof has been cut into and I’ve used the phrase “rigging sub” in conversation more than once, so this is certainly a flurry of activity that’s exciting for us all.

The unit is on track to ship from Texas in mid-May, which means that we are tentatively planning (key word, as ever, being tentatively. Imagine me adding that to the end of every sentence of this email. I won’t do it because that would be annoying, but that’s the kind of looming caveat I’m talking about) for an installation date of May 27.

So how does an HVAC unit that sounds like a Star Wars droid make it onto to the roof? With the help of a huge crane (hence my new friend, the rigging sub!) that will lift it from the top level of the parking lot to the roof, at which point the actual installation will happen.



Will this mean changes in Library services? Yes, but they will hopefully be brief (fingers crossed!).

Again, that word: tentative. At this point in time, this is the projected installation date and our opening time if all goes smoothly. The date may change, and the opening time may get pushed back; you’ll hear via email and our website if that’s the case. We appreciate you being flexible!

Our retaining wall project is moving according to schedule and is currently in the Bidding Process.


What’s bidding? I’m so glad you asked! Bidding was one of those things that I ephemerally knew existed but couldn’t explain until I was involved in it and now I am just schooling everyone I know, much to their chagrin. If you’re already well versed in planning public projects, you can scroll past this, but if you’re interested in learning, here’s a quick primer.


Tentatively (there’s that word again!) work is predicted to start in mid-June. There will be disruptions to programs, services, and functions. We will keep you updated on the details of all of these disruptions as soon as we know them. We thank you in advance for your patience, cooperation, and grace throughout this and the projects to follow.

The interior work is also progressing quite nicely according to our anticipated schedule. We’re heading into the final part of the Construction Documents phase and at that point, the next round of approvals will head to SED’s OFP (State Education Department Office of Facilities Planning, but you knew that) for approvals. Getting approvals from SED is the first step in (a) getting building permits but also (b) applying for grant funding, which is a major priority for us.


As ever, please reach out to us if you have any questions or comments about the project--or anything library-related. We love to hear from you!