Dear Members,
Update for Day 8, June 1st, of the Single Family HOA Roadway Repaving Project. As previously mentioned, the schedule for repaving is dependent on the weather.
The Contractor has completed all of Barclay Lane and has started at the west end of Amberwood with the initial course. Completion of the roadway with the initial and final course should be done by end of day Friday, June 2nd.
After Amberwood, they will move on to Rolling Oaks. We will let everyone know if this changes based on the work tomorrow.
Remember, during the paving operation, roadway access will be limited to local residents only. Remember, once the final paving is installed on that roadway, please don’t travel on the roadway for about 24 hours or have any vehicles parked on the roadway as the tires might leave indentations. If you must drive on the roadway, please be careful. For example, do not turn your front wheels of the car while stopped on the pavement as that will leave a mark.
As we mentioned previously, due to the heavy weight of the garbage trucks, they will not be on any our streets this Friday, June 2, but will be back next Tuesday, June 6th for normal pickups.
We will keep you informed of the progress and schedule with an email tomorrow.
Thank you,
The Strand Single Family HOA Board of Directors
|