The MLK drainage feature is a little known canal that drains the Justice Center on Columbia St. BENEATH Larry's Hardware, under Florida Street near the cemetery and then becomes subsurface culverts past the Department of Children and Family Services (DCFS) and Diamond L Western Wear's parking lot (aka behind Pasquale's).
| | | Decades ago, the natural drainage to the river ran through the future home of the Bogue Falaya Mall. Hence, it was re-routed during construction. More recently, the culvert system began to fail … threatening the structural integrity of the DCFS building. Hence, a $210,000 project replacing and relocating the culverts became a project for which we did not ask for. | | Complicating the work was a shed located on the drainage servitude that serves as a home for one of our residents. It would have to be moved but it was readily apparent the owners did not have the means to pay to do so. By law, city funds cannot (and should not) be used for such work on private property. Not to be thwarted, Fire Chief Steven Michel and Director of Public Works Jim O'Berry reached into their own pockets to pay for the building to be moved. To assist and oversee the move, each took a personal vacation day, as doing so on city time is also disallowed. City Engineer Callie Baker also took a personal day (accompanied by her husband, James). Good people doing good stuff. | | |
Downtown Paving Projects
Phase I
| | |
Prior to repaving any roadway, the City assesses the subterranean infrastructure (particularly sewer lines and subsurface drainage). The hope is to make as many repairs as feasible BEFORE covering it with a new layer of asphalt. This process is tedious, time consuming and common sense.
The underground drainage culverts beneath Gibson and Rutland are close to being replaced. New concrete base is poured atop each replacement. Soon terracotta clay sewer pipes will be CIPP-lined (Cured in Place Plastic), ostensibly giving us "new" sewer lines under the roads.
I hate timelines but will say, IF everything stays on schedule, this project should be finished by the end of the year.
| | | |
Downtown Paving Projects
Phase II
| | New Hampshire, Columbia, Florida, Lee Rd and Lockwood | |
Smoke testing of these streets revealed a large number of failures in the sewer collection system … primarily where lines running from the property owner connect with the main sewer lines.
Our engineering department conceived the idea that these be repaired at the same time the street is being milled down for overlay. A scope of work to that effect is being created.
Our engineering department consists of 4 people focused on projects: an engineer, an intern, a projects manager and a project inspector. My early experience as mayor taught me that this small department can only properly supervise a limited number of projects at a time and do so correctly. As such, I refuse to allow them to begin a new project until an existing project is well under way / nearing completion. Sequencing projects in this manner has resulted in much better work product. The replacement of the drainage culverts under Gibson and Rutland, CIPP lining the terracotta sewer lines and then re-paving those roads is a major, complicated, multi-million dollar undertaking. As it now has momentum, the relocation of the failed culverts on MLK Creek which are threatening the foundation of the DCFS building has begun. Once it has momentum, N. Taylor re-paving will go out to bid followed by New Hampshire, Columbia and Florida Streets. This sequence is not all inclusive of the projects currently underway.
| | | |
A number of our police officers have been housed for several years in an old mechanic shop converted to office space. Two or three shared small rooms with equipment stored on top of itself. Not good.
The new PD annex is coming along nicely and will provide a proper workspace. This investment by the Administration, the Council and by our citizens is a testament of our respect and support for Our Blue.
| | | |
Trace Beautification,
Second Line and Ribbon Cutting
| | Hubie Gallagher Tennis Courts | | |
One by one, the City has been upgrading each park across town.
Last year, it became Hubie Gallagher's (HG) turn. After numerous onsite visits and resident input, a few things came to light.
The tennis court was non-functional. The plastic grid surface did not allow the balls to bounce properly. I concluded that we (the city) had gotten our money's worth out of the court that has been there since I was a child.
Of all the possible improvements we could consider at the park, replacing the courts became the priority. During the Fall budget process, Councilman Jimmy Inman and I requested $300,000 from the Council in the 2025 budget. The budget passed in November and the money became allocated on January 1, 2025.
| | |
Demolition and removal of the court was completed "in-house" by our Public Works Department. Whenever we are able to use Public Works' employees and equipment, I estimate we usually save about 60% in cost. That's a good thing.
| |
Strong consideration was given to pickle ball. Unfortunately, the constant pop-pop-pop sound of the ball against the paddles is not a nice thing in a residential neighborhood. We have a site chosen at the Rec Park near the baseball fields, but no timeline. We need for a number of these current projects to get well underway before considering pickle ball from both a financial and a time-management perspective.
The foundation for the new courts has been poured. Hopefully we'll have new courts by Christmas : )
| | |
Per Fire Chief Steven Michel, "Fire Management Systems will begin testing many of our hydrants this week.
Inspections:
This year they hired some part time help and we are going to have (2) zones start simultaneously. (Zone maps attached)
Inspection process is to make sure the hydrant is worthy of being in-service, point out issues, and make sure it flows water. If problems arise, they report it to me, and I get with Adam to get it fixed. This process has worked well over the last few years.
Please note, we have not had any complaints from residences. This includes the company being unprofessional nor brown water. Impressive.
Flow Tests:
I will send an update on this later. We will start this mid to late November. Part of this will be done in Downtown and performed at night due to traffic and also to not interrupt City Businesses. I have spoken with Adam and PW will provide a person to be with them during the night tests.
Police:
I am requiring the company, at a minimum, to wear a company shirt during inspections/testing. They don’t all have a marked truck, so if you get a complaint of a vehicle or person messing with the Hydrants, you have an idea."
| | |
Phone Keys Wallet
An Atlanta Porch Fest Favorite
| | |
Knights of Columbus
Annual Coat Collection
| | |
It's that time of the year again! St. Peter's Knights of Columbus are collecting new and slightly-used coats/jackets/sweaters for the needy in Covington, with distribution at Thanksgiving (The Little Blue House) and Christmas (Starlight Baptist Church).
Boxes are already inside Acquistapace's, Rouses (Goodbee and Claiborne Hill), the YMCA and the entrance to St. Peter Church. They collected 602 coats last year thanks to the support of our community.
So, go grab those jackets and sweaters now and put them in your car so they will be with you when you arrive at one of the donation locations : ).
| | |
C-4 Explosion - October 25th
Final Friday Block Party - October 31st
| | |
November / December Newsletter
Page 3 - Calendar of Events
| | |
Northshore Food Bank
Pallets With Purpose
| | Mayor Mark's History Corner | |
At 8:30am on the 3rd Tuesday of each month, Lake Radio 94.7 has me as a guest. Most recently, I gave my interpretation of the Louisiana Purchase and the Republic of West Florida. Here's 8 minutes and 43 seconds of your life you'll never get back: